Certificate ⁦10⁩ — August 2026

New Premium Members Centre & VIP lounges — fit-out

Kingdom of Saudi Arabia

Riyadh Chamber of Commerce & Industry

General Directorate of Finance & Procurement — Contracts & Procurement Department

Certificate no.
10
Date
⁦2026-09-16⁩
Hijri
5 Rabiʻ II 1448 AH
Reference
PAY-2025-023-10

Interim payment certificate no. (⁦10⁩)

For the work of August 2026

Contract number
RC/2025/023
Supplier-portal reference
2504720693
Contract
New Premium Members Centre & VIP lounges — fit-out
Contractor
Coastline Contracting & Development Co.
Contractor VAT number
340303951060003
Project
New Premium Members Centre & VIP Lounges
Contract period
⁦2025-04-06⁩ — ⁦2027-02-28⁩
Original contract value
5,900,000
Current contract value
5,900,000
Linked milestone
MEP systems installed · MS-G4 Testing & acceptance complete

Certificate summary (SAR)

1Total value of work completed to date3,245,000
2Less: previous certificates(3,072,000)
3Value of work in this certificate173,000
4Less: retention (⁦10%⁩)(17,300)
5Less: advance payment recovery (⁦10%⁩)(17,300)
6Less: delay and breach penalties0
7Total deductions(34,600)
8Net before VAT138,400
9Add: value added tax (15%)20,760
10Net amount payable to the contractor159,160

Amount in words: One hundred fifty-nine thousand one hundred sixty Saudi riyals only

Retention held up to this certificate: SAR 324.5K — released after final acceptance.

Work by contract item

ItemItem valuePreviousThis periodTo dateComplete
Preliminaries & mobilisation413,000395,70017,300413,000⁦100%⁩
Earthworks & foundations1,062,000887,10041,700928,800⁦87%⁩
Concrete & structural works1,829,0001,047,00059,5501,106,550⁦61%⁩
Mechanical, electrical & plumbing1,416,000509,35035,800545,150⁦38%⁩
Finishes & external works885,000203,05016,000219,050⁦25%⁩
Testing & commissioning295,00029,8002,65032,450⁦11%⁩
Total5,900,0003,072,000173,0003,245,000⁦55%⁩

Amounts in Saudi riyals.

Signatures and approvals

Contractor’s representative

Eng. Talal H. Al-Ghamdi

Al-Ghamdi⁦2026-09-16⁩

Supervising engineer

Eng. Ibrahim A. Al-Ghamdi

Al-Ghamdi⁦2026-09-18⁩

Project manager

Eng. Fahad T. Al-Sulami

Al-Sulami⁦2026-09-21⁩

Finance & contracts

Khalid N. Al-Mutairi

Al-Mutairi⁦2026-09-24⁩

Final approver

Dr. Abdullah S. Al-Qahtani

Al-Qahtani⁦2026-09-27⁩
Issued electronically through Munjaz Integration-ready for the Dynamics 365 supplier portal

Approval chain

Fully approved and sent for payment

  1. Certificate submitted⁦2026-09-16⁩

    Eng. Talal H. Al-Ghamdi

  2. Engineer verifies quantities⁦2026-09-18⁩

    Eng. Ibrahim A. Al-Ghamdi · Director, Engineering Supervision of Construction Projects

    Took 2 days

  3. Project manager certifies⁦2026-09-21⁩

    Eng. Fahad T. Al-Sulami · Senior Project Manager — Branches & Service Centres

    Took 3 days

  4. Payment order prepared⁦2026-09-24⁩

    Khalid N. Al-Mutairi · Senior Finance & Procurement SpecialistPayment request creator

    Took 3 days

  5. Final approval⁦2026-09-27⁩

    Dr. Abdullah S. Al-Qahtani · Secretary-General

    Took 3 days

You are viewing as Dr. Noura M. Al-Otaibi

Linked milestone & deliverables

The certificate is paid against a contract milestone, tied to the project’s milestone and its deliverables

  1. Contract milestoneMEP systems installedLate · ⁦2026-09-29⁩
  2. Project milestoneMS-G4Testing & acceptance completeMilestone not approved yet

Deliverables & completion certificates

Not every completion certificate is issued yet — the amount tied to the milestone is not released before its deliverables are accepted.

Segregation of duties

The platform checks these rules on every certificate

  • The payment request’s creator does not approve itKhalid N. Al-Mutairi → Dr. Abdullah S. Al-Qahtani
  • Whoever verified quantities does not prepare the payment orderEng. Ibrahim A. Al-Ghamdi → Khalid N. Al-Mutairi
  • The project manager does not approve the paymentEng. Fahad T. Al-Sulami → Dr. Abdullah S. Al-Qahtani

Certificate history

27 September 2026

  1. Payment: Dr. Abdullah S. Al-Qahtani signed “Final approval”

    2026-09-27 13:00

24 September 2026

  1. Approval: Khalid N. Al-Mutairi signed “Payment order prepared”

    2026-09-24 13:00

21 September 2026

  1. Approval: Eng. Fahad T. Al-Sulami signed “Project manager certifies”

    2026-09-21 13:00

18 September 2026

  1. Approval: Eng. Ibrahim A. Al-Ghamdi signed “Engineer verifies quantities”

    2026-09-18 13:00

16 September 2026