PRJ-2026-006Off track4ExecutionConstructionStalled

Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

Remove from watchlist

A full branch serving the factories of the Second Industrial City — membership, attestation and certificates of origin — with 40 service desks and training rooms; it needs ground improvement and Riyadh Region Municipality permits.

Early warning: ⁦84%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 14.3M

Actual cost

SAR 6.3M

⁦44%⁩ of budget

Progress

⁦39%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 16.1M

SAR +1.8M

SPI · CPI

0.78Schedule performance index · 0.780.89Cost performance index · 0.89

Forecast finish

⁦2027-07-04⁩

95 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate3 July 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate1 September 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate30 January 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Chamber Branch & Manufacturers’ Service Centre — Second Industrial City

PRJ-2026-006 · Member Experience & Business Development Sector · Strategic · WP-2024-006

StalledOff track4ExecutionProject manager: Eng. Fahad T. Al-Sulami · Sponsor: Eng. Sami A. Al-Fraih
Progress
⁦39%⁩ / ⁦50%⁩
SPI · CPI
0.78 · 0.89
Spend
SAR 6.3M / SAR 14.3M
Estimate at completion
SAR 16.1M

Schedule

⁦11%⁩ behind⁦39%⁩

Planned to date ⁦50%⁩

Forecast finish: 2027-07-0429 Muharram 1449 AH · 95 days late

SPI0.78Schedule performance index · 0.78CPI0.89Cost performance index · 0.89

Health dimensions

Off track

Last update: 2026-10-2312 Jumada I 1448 AH · Up to date

Deliverables

⁦4⁩ of ⁦9⁩ due deliverables accepted on time (⁦44%⁩)

Next milestones

  • Build complete2027-01-113 Shaʻban 1448 AH
  • Testing & acceptance complete2027-04-2316 Dhuʻl-Qiʻdah 1448 AH
  • Final handover2027-06-3025 Muharram 1449 AH

Top risks

  • Ground-improvement costs up after the geotechnical survey16
  • Late building permits from the Riyadh Region Municipality12

Open impediments

  • Foundation works stopped pending building permits · Escalated
  • Neighbouring factories objecting to the car-park entrance · Open

Decisions and changes waiting

  • CR-2026-007 · Additional ground improvement after the geotechnical survey

Copilot summary

The scope holds 1 project with a budget of SAR 14.3M: 0 on track and 1 red or critical. Weighted progress is 39% against 50% planned, spend SAR 6.3M, and EAC SAR 16.1M (SAR 1.8M over).

1 project is more than a month behind baseline; the worst: Chamber Branch & Manufacturers’ Service Centre — Second Industrial City (95 days).

Riyadh Chamber of Commerce & Industry · prepared by Eng. Fahad T. Al-Sulami in MunjazInternal

Status: Off track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close