Riyadh Chamber Mobile App — New Release
Add to watchlistThe most-used services, the digital membership card, a wallet of certificates and attestations, and event and committee alerts.
Budget (BAC)
Actual cost
62% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure23 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-01-21 | 2026-03-07 | +45 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-15 | 2026-07-02 | +78 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-08-17 | 2026-11-11 | +86 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-11-09 | 2026-12-19 | +40 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-01-31 | 2027-01-31 | On time | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
64%Awaiting acceptance
10%Not handed in
26%Deliverable flow
Display options
| Project plan & baseline015-D1 | 5% | CRT-015-01 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Faisal A. Al-Shehri | 2025-12-11 | V1 | 3 of 3 |
| Monitoring & reporting015-D2 | 5% | CRT-015-02 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.sa | Faisal A. Al-Shehri | 2026-01-21 | V1 | 3 of 3 |
| Business requirements015-D3 | 11% | CRT-015-03 | Approved | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.sa | Faisal A. Al-Shehri | 2026-03-04 | V1 | 3 of 3 |
| Solution design015-D4 | 11% | CRT-015-04 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Faisal A. Al-Shehri | 2026-04-15 | V1 | 3 of 3 |
| Release 1015-D5 | 16% | CRT-015-05 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Faisal A. Al-Shehri | 2026-05-26 | V1 | 3 of 3 |
| Release 2015-D6 | 16% | CRT-015-06 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Faisal A. Al-Shehri | 2026-07-07 | V1 | 3 of 3 |
| Integrations015-D7 | 10% | — | Under review | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.sa | Faisal A. Al-Shehri | 2026-08-17 | V1 | 1 of 3 |
| System testing015-D8 | 7% | — | Draft | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Faisal A. Al-Shehri | 2026-09-28 | V0 | 0 of 3 |
| User acceptance testing015-D9 | 7% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.sa | Faisal A. Al-Shehri | 2026-11-09 | V0 | 0 of 3 |
| Training & change015-D10 | 6% | — | Draft | Faisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.sa | Faisal A. Al-Shehri | 2026-12-20 | V0 | 0 of 3 |
| Go-live & handover015-D11 | 6% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Faisal A. Al-Shehri | 2027-01-31 | V0 | 0 of 3 |
| Total · 11 | 100% |