Riyadh Chamber Mobile App — New Release

Add to watchlist

The most-used services, the digital membership card, a wallet of certificates and attestations, and event and committee alerts.

Budget (BAC)

SAR 630K

Actual cost

SAR 388K

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 606K

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

The most-used services, the digital membership card, a wallet of certificates and attestations, and event and committee alerts.

In scope

  • The most-used services, the digital membership card, a wallet of certificates and attestations, and event and committee alerts.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-10-28⁩

    Baseline approved at the planning gate

    Budget630KFinish⁦2027-01-31⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional2
  • Technical1
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦17%⁩

1/6 · test result is a pass

Accepted

⁦17%⁩

1/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-015-01An end-to-end digital journey, no walk-inBusinessMustApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.saSB-1
REQ-015-02Nafath single sign-onFunctionalMustApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saSB-1
REQ-015-03A user dashboardFunctionalMustIn progressFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.saSB-1
REQ-015-04Integration with internal systemsTechnicalShouldIn progressKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saSB-1
REQ-015-05⁦WCAG 2⁩.⁦1⁩ accessibilityRegulatoryCouldApprovedFaisal A. Al-ShehriFaisal A. Al-ShehriDirector General, Digital Services & Portfolio Manager, Digital Services & Member ExperienceP-003f.alshehri@chamber.saSB-1
REQ-015-06Essential cybersecurity controlsSecurityCouldIn progressKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.