PRJ-2026-015On track4ExecutionScrumIn progress

Riyadh Chamber Mobile App — New Release

Add to watchlist

The most-used services, the digital membership card, a wallet of certificates and attestations, and event and committee alerts.

Budget (BAC)

SAR 630K

Actual cost

SAR 388K

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 606K

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 630K split into spent, committed and left, with the estimate at completion

EAC SAR 606K
Revised request SAR 630K
  • Actual spendSAR 388K
  • Committed, not spentSAR 157K
  • Allotted, uncommittedSAR 66.1K
  • Contingency availableSAR 18.9K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 610K
Original budgetwhen the first baseline was approved
SAR 630K
Approved budgetafter approved change requests
SAR 630K
Current budgetavailable to spend now
SAR 630K
Revised budgetif the pending changes are approved
SAR 630K

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 545K
Contracts1 active contract
SAR 490K
Purchase orders⁦2⁩ orders
SAR 55K
Remaining budgetapproved less actual
SAR 242K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 388K
Accrualswork done, not yet invoiced
SAR 16K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 606K
ContingencySAR 13.1K drawn of SAR 32K
SAR 18.9K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 610K
ApprovedSAR 630K
Estimate at completionSAR 606K
Approved is SAR 20K (⁦3.3%⁩) above the estimate
The estimate at completion is SAR 4,000 (⁦0.7%⁩) below the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-07-22⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-41015
  • WBS elements⁦5⁩ elements · P-2026-015.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦8⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 13.1K drawn of SAR 32K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 13.1K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.050.050.050.05⁦+0.00⁩
2Analysis & design0.100.100.100.10⁦−0.00⁩
3Build0.240.240.240.24⁦+0.00⁩
4Testing & acceptance0.120.090.000.11⁦+0.01⁩
5Launch & handover0.090.070.000.09⁦+0.01⁩
Unallocated contingency0.020.000.000.01⁦+0.01⁩
Total0.630.550.390.61⁦+0.02⁩

Budget split

WBS

SAR 630K

Budget

  • Management & governanceSAR 48.9K⁦8%⁩
  • Analysis & designSAR 103.9K⁦16%⁩
  • BuildSAR 244.4K⁦39%⁩
  • Testing & acceptanceSAR 122.2K⁦19%⁩
  • Launch & handoverSAR 91.7K⁦15%⁩
  • Unallocated contingencySAR 18.9K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-07-27⁩+177

SPI(t) ⁦0.73⁩ against the approved finish ⁦2027-01-31⁩

Planned valuePV
SAR 572K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 403K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 388K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 630K
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.02⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.17⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.04
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.70
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 606K
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 218K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.02⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.94
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 606.6K
  • If the rest goes to planSAR 615K
  • At cost and schedule performanceSAR 698.2K
  • The PM’s bottom-up estimateSAR 606K
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 606.3K

Variance at completion: ⁦+0.02⁩ SAR M