Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-015On track4ExecutionScrumIn progress

Riyadh Chamber Mobile App — New Release

Add to watchlist

The most-used services, the digital membership card, a wallet of certificates and attestations, and event and committee alerts.

Budget (BAC)

SAR 630K

Actual cost

SAR 388K

⁦62%⁩ of budget

Progress

⁦64%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 606K

SPI · CPI

1.02Schedule performance index · 1.021.04Cost performance index · 1.04

Forecast finish

⁦2027-01-28⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure23 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate5 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate21 December 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate23 December 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦0⁩ days vs approved

Baseline (original = approved) · Current forecast⁦2027-01-31⁩
By earned schedule⁦2027-07-27⁩
Critical activities
1
of ⁦8⁩ open activities
Late activities
4
past their baseline finish
Schedule performance
0.70
earned ÷ planned value
Next milestone
in 14 days
Build complete
Expand allCollapse all
Activity
Riyadh Chamber Mobile App — New ReleasePlanned: ⁦2025-10-05⁩ → ⁦2027-01-31⁩Forecast: ⁦2025-10-05⁩ → ⁦2027-01-31⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-10-05⁩ → ⁦2026-01-21⁩Actual: ⁦2025-10-05⁩ → ⁦2026-03-07⁩
Project plan & baselinePlanned: ⁦2025-10-05⁩ → ⁦2025-12-11⁩Actual: ⁦2025-10-05⁩ → ⁦2026-01-07⁩
Monitoring & reportingPlanned: ⁦2025-11-16⁩ → ⁦2026-01-21⁩Actual: ⁦2025-12-03⁩ → ⁦2026-03-07⁩
Project plan approvedPlanned: ⁦2026-01-21⁩ → ⁦2026-01-21⁩Actual: ⁦2026-03-07⁩ → ⁦2026-03-07⁩Project plan approved
Analysis & designPlanned: ⁦2025-12-27⁩ → ⁦2026-04-15⁩Actual: ⁦2026-01-30⁩ → ⁦2026-07-02⁩
Business requirementsPlanned: ⁦2025-12-27⁩ → ⁦2026-03-04⁩Actual: ⁦2026-01-30⁩ → ⁦2026-05-04⁩
Solution designPlanned: ⁦2026-02-07⁩ → ⁦2026-04-15⁩Actual: ⁦2026-03-30⁩ → ⁦2026-07-02⁩
Designs approvedPlanned: ⁦2026-04-15⁩ → ⁦2026-04-15⁩Actual: ⁦2026-07-02⁩ → ⁦2026-07-02⁩Designs approved
BuildPlanned: ⁦2026-03-21⁩ → ⁦2026-08-17⁩Forecast: ⁦2026-05-28⁩ → ⁦2026-11-11⁩Float: ⁦5⁩d
Release 1Planned: ⁦2026-03-21⁩ → ⁦2026-05-26⁩Actual: ⁦2026-05-28⁩ → ⁦2026-08-30⁩
Release 2Planned: ⁦2026-05-01⁩ → ⁦2026-07-07⁩Actual: ⁦2026-07-26⁩ → ⁦2026-10-26⁩
IntegrationsPlanned: ⁦2026-06-12⁩ → ⁦2026-08-17⁩Forecast: ⁦2026-06-12⁩ → ⁦2026-11-11⁩Float: ⁦5⁩dDrag to change its duration+86
Build completePlanned: ⁦2026-08-17⁩ → ⁦2026-08-17⁩Forecast: ⁦2026-11-11⁩ → ⁦2026-11-11⁩Float: ⁦81⁩dDrag to change its datesBuild complete
Testing & acceptancePlanned: ⁦2026-07-23⁩ → ⁦2026-11-09⁩Forecast: ⁦2026-10-30⁩ → ⁦2026-12-19⁩Float: ⁦5⁩d
System testingPlanned: ⁦2026-07-23⁩ → ⁦2026-09-28⁩Forecast: ⁦2026-10-30⁩ → ⁦2026-11-30⁩Float: ⁦5⁩dDrag to change its dates+63
User acceptance testingPlanned: ⁦2026-09-03⁩ → ⁦2026-11-09⁩Forecast: ⁦2026-11-18⁩ → ⁦2026-12-19⁩Float: ⁦5⁩dDrag to change its dates+40
Testing & acceptance completePlanned: ⁦2026-11-09⁩ → ⁦2026-11-09⁩Forecast: ⁦2026-12-19⁩ → ⁦2026-12-19⁩Float: ⁦43⁩dDrag to change its datesTesting & acceptance complete
Launch & handoverPlanned: ⁦2026-10-15⁩ → ⁦2027-01-31⁩Forecast: ⁦2026-12-07⁩ → ⁦2027-01-31⁩Float: ⁦0⁩d
Training & changePlanned: ⁦2026-10-15⁩ → ⁦2026-12-20⁩Forecast: ⁦2026-12-07⁩ → ⁦2027-01-07⁩Float: ⁦5⁩dDrag to change its dates+18
Go-live & handoverPlanned: ⁦2026-11-25⁩ → ⁦2027-01-31⁩Forecast: ⁦2026-12-26⁩ → ⁦2027-01-26⁩Float: ⁦5⁩dDrag to change its dates
Final handoverPlanned: ⁦2027-01-31⁩ → ⁦2027-01-31⁩Forecast: ⁦2027-01-31⁩ → ⁦2027-01-31⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦22⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦8⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦0⁩ activities with no float

Every day lost on this chain is a day lost at launch. ⁦5⁩ more activities have three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 50 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

45
78
86
40
0
G1G2G3G4G5

The critical chain

In date order, to final acceptance

Near-critical

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close