PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2025-04-27⁩
Hijri
29 Shawwal 1446 AH
ApprovedCRT-017-01Project plan & baseline

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Correspondence & Document Management System
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The deliverableAuto-filled

DeliverableAuto-filled
Project plan & baseline
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Dana S. Al-Saleh
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦4%⁩
DueAuto-filled
⁦2025-04-14⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-017_1.1_v1.pdfV1Dana S. Al-Saleh⁦2025-01-19⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Munirah A. Al-Khalidi
Accepted byAuto-filled
Sarah A. Al-Qarni
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Project plan approved
ContractAuto-filled
CTR-2025-019
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2025-01-19⁩ 12:09
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-01-21⁩ 14:59
3Inspection & technical acceptance — ownerTechnical acceptanceSarah A. Al-QarniProject ownerOn behalf of Munirah A. Al-KhalidiApprovedInspected and accepted against the approved acceptance criteria.⁦2025-01-22⁩ 09:06
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-01-23⁩ 13:04
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-01-27⁩ 14:41

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-01-21⁩

Inspection & technical acceptance — owner

Sarah A. Al-Qarni

Approved⁦2025-01-22⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-01-23⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-01-27⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2025-01-19⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-01-21⁩ at ⁦14:59⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Munirah A. Al-Khalidi · Project owner

    Approved · ⁦2025-01-22⁩ at ⁦09:06⁩ · On behalf of Munirah A. Al-Khalidi (Sarah A. Al-Qarni)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-01-23⁩ at ⁦13:04⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-01-27⁩ at ⁦14:41⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-01-19⁩

    PRJ-2026-017_1.1_v1.pdf

    Dana S. Al-Saleh

Only one version so far.