PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Priority evaluation

Criteria, weights and the P1–P4 result

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Priority evaluation

Criteria, weights and the P1–P4 result

Form no.
RC-PMO-F02
Template edition
1.3
Version
V4
Form date
⁦2024-08-17⁩
Hijri
13 Safar 1446 AH
ApprovedPRJ-2026-017Correspondence & Document Management System

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Correspondence & Document Management System
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The resultAuto-filled

Priority score

62 of 100

Class

P2

60–74

Priority model

Version 4

Class thresholdsAuto-filled

P1 from 75 · P2 from 60 · P3 from 45 · P4 below 45

2Criteria and weightsAuto-filled

Rated 1–5; the cost criteria (risk, complexity, resources) are turned around before weighting.

CriterionWeightRatingPoints
Fit with the chamber’s strategy⁦20%⁩4.417.0
Value added to the business community⁦12%⁩3.88.4
Financial return & sustainability⁦8%⁩3.44.8
Urgency⁦10%⁩3.35.7
Regulatory requirement⁦10%⁩1.61.5
Risk⁦7%⁩2.05.3
Complexity⁦6%⁩2.04.5
Resource requirement⁦5%⁩1.05.0
Impact on members & beneficiaries⁦14%⁩3.17.3
Sustainability impact⁦3%⁩2.00.8
Digital transformation impact⁦5%⁩2.21.5
Total⁦100%⁩—62

Approval logChain: Priority evaluation approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleSubmitted—⁦2024-08-17⁩ 11:08
2Evaluation checked against the modelMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2024-08-18⁩ 09:12
3Portfolio manager reviewTechnical acceptanceEng. Nayef H. Al-BuqamiPortfolio managerApproved—⁦2024-08-20⁩ 10:19
4Class approved — Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2024-08-26⁩ 11:26

Signatures

Evaluation checked against the model

Ghada A. Al-Shahrani

Approved⁦2024-08-18⁩

Portfolio manager review

Eng. Nayef H. Al-Buqami

Approved⁦2024-08-20⁩

Class approved — Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2024-08-26⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F02 · version V4

Priority evaluation

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Priority evaluation approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2024-08-17⁩

  1. Methodology review

    Evaluation checked against the model

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2024-08-18⁩ at ⁦09:12⁩

  2. Technical acceptance

    Portfolio manager review

    Eng. Nayef H. Al-Buqami · Portfolio manager

    Approved · ⁦2024-08-20⁩ at ⁦10:19⁩

  3. Technical acceptance

    Class approved — Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2024-08-26⁩ at ⁦11:26⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V4ApprovedCurrent⁦2024-08-17⁩

    Evaluated on the approved priority model

    Ghada A. Al-Shahrani

Only one version so far.