Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
RC-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-01-26⁩
Hijri
26 Rajab 1446 AH
ApprovedMTG-KO-017Kick-off — Correspondence & Document Management System

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Correspondence & Document Management System
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Correspondence & Document Management System
Date and timeAuto-filled
⁦2025-01-26⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Dana S. Al-Saleh

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Sarah A. Al-QarniAssistant Secretary-General, Support Services
Munirah A. Al-KhalidiDirector General, Finance & Procurement
Dana S. Al-SalehDirector, Enterprise Systems & Integration
Dr. Noura M. Al-OtaibiDirector, Project Management Office

2Roles

PersonRoleDuty
Sarah A. Al-QarniProject sponsorSponsors the project, decides escalations and material changes
Munirah A. Al-KhalidiProject ownerApproves the requirements and accepts the deliverables
Dana S. Al-SalehProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates

3Tasks

TaskOwnerDueStatus
Project plan approvedDana S. Al-Saleh⁦2025-06-07⁩Done
Designs approvedDana S. Al-Saleh⁦2025-09-21⁩Done
Build completeDana S. Al-Saleh⁦2026-03-01⁩Done
Testing & acceptance completeDana S. Al-Saleh⁦2026-06-15⁩Done

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2025-04-28⁩
Start confirmed
Sarah A. Al-Qarni · ⁦2025-01-27⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Dana S. Al-SalehDirector, Enterprise Systems & IntegrationSubmitted—⁦2025-01-27⁩ 13:40
2Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-01-28⁩ 11:44
3Chair’s approval (sponsor)Technical acceptanceSarah A. Al-QarniProject sponsorApproved—⁦2025-01-28⁩ 12:30

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-01-28⁩

Chair’s approval (sponsor)

Sarah A. Al-Qarni

Approved⁦2025-01-28⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Dana S. Al-Saleh on ⁦2025-01-27⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-01-28⁩ at ⁦11:44⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Sarah A. Al-Qarni · Project sponsor

    Approved · ⁦2025-01-28⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-01-26⁩

    The minutes as taken

    Dana S. Al-Saleh

Only one version so far.