PRJ-2026-017At risk5ClosureWaterfallIn progress

Correspondence & Document Management System

Add to watchlist

Incoming and outgoing correspondence automated, with an archive of the chamber’s documents and its board and committee minutes.

Budget (BAC)

SAR 710K

Actual cost

SAR 675K

⁦95%⁩ of budget

Progress

⁦95%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 710K

SPI · CPI

0.95Schedule performance index · 0.951.00Cost performance index · 1.00

Forecast finish

⁦2026-11-15⁩

46 days behind baseline

ClosureStage ⁦5⁩ of ⁦5⁩

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate20 November 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionConditional goDate19 January 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate28 April 2025Execution · CompleteExecution · Complete
  5. Gate into «Closure»DecisionGoDate11 August 2026Closure · Current stageClosure · Current stage

Project closure & handover

Performance, handover, open commitments and lessons learned

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Closure

Project closure & handover

Performance, handover, open commitments and lessons learned

Form no.
RC-PMO-F12
Template edition
2.0
Version
V0
Form date
⁦2026-10-28⁩
Hijri
17 Jumada I 1448 AH
DraftPRJ-2026-017Correspondence & Document Management System

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-017
Project
Correspondence & Document Management System
Portfolio
Technology & Enterprise Systems Portfolio
Sector
Digital Transformation & IT
Sponsor
Sarah A. Al-Qarni
Project manager
Dana S. Al-Saleh

1PerformanceAuto-filled

Approved budget

SAR 710K

Actual cost

SAR 675K

Cost variance

SAR +35K

Schedule variance

+46 days

2HandoverAuto-filled

ItemStateOwnerEvidence
Final acceptance of deliverablesOpenMunirah A. Al-KhalidiFinal acceptance of every deliverable
Financial settlementOpenKhalid N. Al-MutairiSpend reconciled, commitments closed
Contracts closedOpenKhalid N. Al-MutairiContracts closed, retention released
Documents archivedOpenDana S. Al-SalehDocuments archived with classification
Lessons learnedOpenDana S. Al-SalehLessons-learned session
Benefits handed to their ownerOpenMunirah A. Al-KhalidiBenefits handed to their owner with a measurement plan
Final reportOpenDana S. Al-SalehFinal report and its approval
BenefitNew ownerHandover
Faster routing of correspondenceMunirah A. Al-KhalidiPlanned

3Open commitments

CommitmentOwnerDue
Final acceptance of deliverables — Final acceptance of every deliverableMunirah A. Al-Khalidi⁦2026-11-05⁩
Financial settlement — Spend reconciled, commitments closedKhalid N. Al-Mutairi⁦2026-12-05⁩
Contracts closed — Contracts closed, retention releasedKhalid N. Al-Mutairi⁦2026-12-15⁩
Documents archived — Documents archived with classificationDana S. Al-Saleh⁦2026-12-10⁩
Lessons learned — Lessons-learned sessionDana S. Al-Saleh⁦2026-11-30⁩
Benefits handed to their owner — Benefits handed to their owner with a measurement planMunirah A. Al-Khalidi⁦2026-11-25⁩
Final report — Final report and its approvalDana S. Al-Saleh⁦2026-12-20⁩

4Lessons learnedAuto-filled

  1. —

Approval logChain: Project closure & handover approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

No decisions yet — the form has not been submitted.

Signatures

Closure file completeness

Ghada A. Al-Shahrani

Later

Handover accepted — project owner

Munirah A. Al-Khalidi

Later

Final financial settlement

Munirah A. Al-Khalidi

Later

Contracts closed, guarantees released

Mazen A. Al-Hazmi

Later

Project Approval Committee

Dr. Noura M. Al-Otaibi

Later

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F12 · version V0

Project closure & handover

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project closure & handover approval · version ⁦1⁩

Not submitted for approval yet.

  1. Methodology review

    Closure file completeness

    Ghada A. Al-Shahrani · PMO — analyst

    Delegated to Dr. Noura M. Al-Otaibi

  2. Technical acceptance

    Handover accepted — project owner

    Munirah A. Al-Khalidi · Project owner

    Delegated to Khalid N. Al-Mutairi

  3. Financial approval

    Final financial settlement

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Delegated to Khalid N. Al-Mutairi

  4. Financial approval

    Contracts closed, guarantees released

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee
Waiting on Dana S. Al-Saleh

Previous versions

Every version is kept with its status and what changed.

  1. V0DraftCurrent⁦2026-10-28⁩

    The closure file in preparation

    Dana S. Al-Saleh

Only one version so far.