Original
Original baseline
- Finish
- 2027-01-31
- Budget
- SAR 6.6M
- 17 activities
Approved with the project plan at the planning gate.
Approved 2025-05-11 · by Eng. Majed S. Al-Rasheed
Fibre and backup links to 14 sites: headquarters, the branches, the service points and the training complex.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SAR +204K
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure12 December 2026
The original, the approved revised and the working baseline, with any two versions compared on dates and cost. An approved baseline is locked and moves only through a change request; every version is kept.
Original
Approved with the project plan at the planning gate.
Approved 2025-05-11 · by Eng. Majed S. Al-Rasheed
Working
Follows the latest schedule and cost forecast; becomes approved only through a change request the CCB passes.
Created 2026-10-28 · by Eng. Omar H. Bawazir
What changed from version A to version B
Finish
2027-01-312027-03-01
+29 days
Budget
SAR 6.6MSAR 6.7M
+0.06 SAR M
Milestones moved
5 / 5
Each line starts at the milestone’s date in A and ends at its date in B
Version AVersion B
Difference in SAR millions from A to B
Every saved version with its reason and reference