PRJ-2026-018At risk4ExecutionConstructionIn progress

Unified Enterprise Network for HQ & the Branches

Add to watchlist

Fibre and backup links to 14 sites: headquarters, the branches, the service points and the training complex.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 6.6M

Actual cost

SAR 3.7M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.8M

SAR +204K

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Team & roles

1 member, about ⁦0.3⁩ full-time equivalents

Leadership

1 member

  • Eng. Omar H. BawazirProject manager⁦35%⁩Allocated ⁦115%⁩ across all projectsA

A AccountableR ResponsibleC ConsultedI Informed

Stakeholders

⁦6⁩ stakeholders, ⁦5⁩ of them below the engagement needed

Power / interest matrix

Pick one to see how they are handled

Power & influence

Keep satisfied1

high power, lower interest

Manage closely4

high power and interest

Monitor0

minimal effort

Keep informed1

high interest, lower power

Eng. Majed S. Al-RasheedManage closelyEng. Nayef H. Al-BuqamiManage closelyProject Management Office (PMO)Manage closelyEnd beneficiariesKeep informedGeneral Directorate of Financial AffairsKeep satisfiedSmart Link Telecom & Security Systems Co.Manage closely

Interest

Project sponsor

Eng. Majed S. Al-Rasheed

Decisions and funding

Influence

Interest

Engagement level

Unaware

Resistant

Neutral

Now

Supportive

Target

Leading

A gap of ⁦1⁩ step — needs an engagement plan.

Impact on the project
Approves gates and changes
Engagement plan
Monthly briefing
Last contact⁦2026-09-15⁩
⁦6⁩ results
Export CSV
OrganisationRoleActions
Eng. Majed S. Al-RasheedProject sponsorDecisions and fundingSupportiveLeadingEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa⁦2026-09-15⁩
Eng. Nayef H. Al-BuqamiProject ownerAccepts deliverables, owns benefitsNeutralLeadingEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa⁦2026-09-18⁩
Project Management Office (PMO)GovernanceCompliance and data qualitySupportiveEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa⁦2026-09-12⁩
General Directorate of Financial AffairsInternal departmentPayment approvalNeutralSupportiveHaifa S. Al-RuwailiHaifa S. Al-RuwailiSenior Financial AnalystP-037h.alruwaili@chamber.sa⁦2026-09-09⁩
Smart Link Telecom & Security Systems Co.Main vendorDelivers the contracted workNeutralSupportiveEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa⁦2026-09-19⁩
End beneficiariesBeneficiariesUsers of the outcomeNeutralSupportiveEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa⁦2026-08-22⁩
⁦1⁩–⁦6⁩ of ⁦6⁩

Communication plan

Who needs what, when, through which channel, and who owns it.

  • Project sponsorStatus and decisions neededMonthlyMeetingEng. Omar H. Bawazir⁦2026-10-11⁩
  • Project ownerDeliverable status and acceptance datesFortnightlyEmailEng. Omar H. Bawazir⁦2026-09-29⁩
  • PMOData and indicator updatesWeeklyDashboardEng. Omar H. Bawazir⁦2026-09-26⁩
  • BeneficiariesWhat changes and whenAt milestonesNewsletterEng. Omar H. BawazirAt launch

Coming up

By date

  1. 262026-09PMODashboard · Weekly
  2. 292026-09Project ownerEmail · Fortnightly
  3. 112026-10Project sponsorMeeting · Monthly