Unified Enterprise Network for HQ & the Branches
Add to watchlistFibre and backup links to 14 sites: headquarters, the branches, the service points and the training complex.
Budget (BAC)
Actual cost
57% of budget
Progress
Estimate at completion
SAR +204K
SPI · CPI
Forecast finish
33 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure12 December 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-09-18 | 2025-12-08 | +81 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-27 | 2026-05-19 | +143 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-26 | 2026-11-11 | +169 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-23 | 2027-01-16 | +85 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-01-31 | 2027-03-01 | +29 days | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
55%Awaiting acceptance
10%Not handed in
35%Deliverable flow
Display options
| Project plan & baseline018-D1 | 4% | CRT-018-01 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | Eng. Nayef H. Al-Buqami | 2025-07-30 | V1 | 3 of 3 |
| Monitoring & reporting018-D2 | 4% | CRT-018-02 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.sa | Eng. Nayef H. Al-Buqami | 2025-09-18 | V1 | 3 of 3 |
| Detailed design018-D3 | 8% | CRT-018-03 | Approved | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.sa | Eng. Nayef H. Al-Buqami | 2025-11-07 | V1 | 3 of 3 |
| Permits & approvals018-D4 | 7% | CRT-018-04 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Eng. Nayef H. Al-Buqami | 2025-12-27 | V1 | 3 of 3 |
| Site works & excavation018-D5 | 16% | CRT-018-05 | Approved | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Eng. Nayef H. Al-Buqami | 2026-02-15 | V1 | 3 of 3 |
| Structure018-D6 | 16% | CRT-018-06 | Approved | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | Eng. Nayef H. Al-Buqami | 2026-04-06 | V1 | 3 of 3 |
| Finishes018-D7 | 10% | — | Under review | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.sa | Eng. Nayef H. Al-Buqami | 2026-05-26 | V1 | 1 of 3 |
| Supply018-D8 | 8% | — | Draft | Eng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.sa | Eng. Nayef H. Al-Buqami | 2026-07-15 | V0 | 0 of 3 |
| Installation018-D9 | 8% | — | Draft | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.sa | Eng. Nayef H. Al-Buqami | 2026-09-03 | V0 | 0 of 3 |
| Testing & commissioning018-D10 | 8% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Eng. Nayef H. Al-Buqami | 2026-10-23 | V0 | 0 of 3 |
| Provisional acceptance018-D11 | 6% | — | Draft | Eng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.sa | Eng. Nayef H. Al-Buqami | 2026-12-12 | V0 | 0 of 3 |
| Final acceptance018-D12 | 5% | — | Draft | Eng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.sa | Eng. Nayef H. Al-Buqami | 2027-01-31 | V0 | 0 of 3 |
| Total · 12 | 100% |