Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-018At risk4ExecutionConstructionIn progress

Unified Enterprise Network for HQ & the Branches

Add to watchlist

Fibre and backup links to 14 sites: headquarters, the branches, the service points and the training complex.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 6.6M

Actual cost

SAR 3.7M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.8M

SAR +204K

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
0On track
1At risk
2Late
Average delay101 days
Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27
Contractual
Build completePlanned: ⁦2026-05-26⁩Forecast / actual: ⁦2026-11-11⁩Delay: 169 daysG3 +169
Executive
Project plan approvedPlanned: ⁦2025-09-18⁩Forecast / actual: ⁦2025-12-08⁩Delay: 81 daysG1 +81
Payment
Final handoverPlanned: ⁦2027-01-31⁩Forecast / actual: ⁦2027-03-01⁩Delay: 29 daysG5 +29
Regulatory
Testing & acceptance completePlanned: ⁦2026-10-23⁩Forecast / actual: ⁦2027-01-16⁩Delay: 85 daysG4 +85
Project
Designs approvedPlanned: ⁦2025-12-27⁩Forecast / actual: ⁦2026-05-19⁩Delay: 143 daysG2 +143

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-09-18⁩⁦2025-12-08⁩⁦+81⁩ daysEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-12-27⁩⁦2026-05-19⁩⁦+143⁩ daysEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-05-26⁩⁦2026-11-11⁩⁦+169⁩ daysEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-10-23⁩⁦2027-01-16⁩⁦+85⁩ daysEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saLate0Not requested
Final handoverMS-G5Payment⁦2027-01-31⁩⁦2027-03-01⁩⁦+29⁩ daysEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saAt risk0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦55%⁩

Awaiting acceptance

⁦10%⁩

Not handed in

⁦35%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline018-D1⁦4%⁩CRT-018-01ApprovedEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saEng. Nayef H. Al-Buqami⁦2025-07-30⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting018-D2⁦4%⁩CRT-018-02ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.saEng. Nayef H. Al-Buqami⁦2025-09-18⁩V1⁦3⁩ of ⁦3⁩
Detailed design018-D3⁦8%⁩CRT-018-03ApprovedEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.saEng. Nayef H. Al-Buqami⁦2025-11-07⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals018-D4⁦7%⁩CRT-018-04ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.saEng. Nayef H. Al-Buqami⁦2025-12-27⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation018-D5⁦16%⁩CRT-018-05ApprovedEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.saEng. Nayef H. Al-Buqami⁦2026-02-15⁩V1⁦3⁩ of ⁦3⁩
Structure018-D6⁦16%⁩CRT-018-06ApprovedEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saEng. Nayef H. Al-Buqami⁦2026-04-06⁩V1⁦3⁩ of ⁦3⁩
Finishes018-D7⁦10%⁩—Under reviewEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.saEng. Nayef H. Al-Buqami⁦2026-05-26⁩V1⁦1⁩ of ⁦3⁩
Supply018-D8⁦8%⁩—DraftEng. Omar H. BawazirEng. Omar H. BawazirDirector, IT InfrastructureP-024o.bawazir@chamber.saEng. Nayef H. Al-Buqami⁦2026-07-15⁩V0⁦0⁩ of ⁦3⁩
Installation018-D9⁦8%⁩—DraftEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.saEng. Nayef H. Al-Buqami⁦2026-09-03⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning018-D10⁦8%⁩—DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.saEng. Nayef H. Al-Buqami⁦2026-10-23⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance018-D11⁦6%⁩—DraftEng. Nayef H. Al-BuqamiEng. Nayef H. Al-BuqamiDirector General, Information TechnologyP-017n.albuqami@chamber.saEng. Nayef H. Al-Buqami⁦2026-12-12⁩V0⁦0⁩ of ⁦3⁩
Final acceptance018-D12⁦5%⁩—DraftEng. Majed S. Al-RasheedEng. Majed S. Al-RasheedExecutive Director, Digital Transformation & ITP-011m.alrasheed@chamber.saEng. Nayef H. Al-Buqami⁦2027-01-31⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close