Early warning: 52% chance of slipping within 45 days
Budget (BAC)
SAR 6.6M
Actual cost
SAR 3.7M
57% of budget
Progress
55%Awaiting acceptance 10%
Estimate at completion
SAR 6.8M
SAR +204K
SPI · CPI
0.87Schedule performance index · 0.870.97Cost performance index · 0.97
Forecast finish
2027-03-05
33 days behind baseline
Execution·Stage 4 of 5
Next gate:Closure12 December 2026
Pre-start · CompletePre-start · Complete
Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started
Schedule & Gantt
The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.
Finish-date drift
+29 days vs approved
Baseline (original = approved)2027-01-31
Current forecast2027-03-01
By earned schedule2028-02-17
Critical activities
7
of 9 open activities
Late activities
6
past their baseline finish
Schedule performance
0.58
earned ÷ planned value
Next milestone
in 14 days
Build complete
Layers
Compare with
Expand allCollapse all
ActivityOwnerForecast finishProgress
2025
2026
2027
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Today
2027-03-0155%
Unified Enterprise Network for HQ & the BranchesPlanned: 2025-05-11 → 2027-01-31Forecast: 2025-05-11 → 2027-03-01Float: 0d