PRJ-2026-018At risk4ExecutionConstructionIn progress

Unified Enterprise Network for HQ & the Branches

Add to watchlist

Fibre and backup links to 14 sites: headquarters, the branches, the service points and the training complex.

Early warning: ⁦52%⁩ chance of slipping within ⁦45⁩ days

Budget (BAC)

SAR 6.6M

Actual cost

SAR 3.7M

⁦57%⁩ of budget

Progress

⁦55%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 6.8M

SAR +204K

SPI · CPI

0.87Schedule performance index · 0.870.97Cost performance index · 0.97

Forecast finish

⁦2027-03-05⁩

33 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure12 December 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate12 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate11 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate20 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate12 December 2026Closure · Not startedClosure · Not started

Schedule & Gantt

The plan with its planned, actual and forecast dates, baselines, links and critical path. The forecast is scheduled from the data date through the links and constraints.

Finish-date drift

⁦+29⁩ days vs approved

Baseline (original = approved)⁦2027-01-31⁩
Current forecast⁦2027-03-01⁩
By earned schedule⁦2028-02-17⁩
Critical activities
7
of ⁦9⁩ open activities
Late activities
6
past their baseline finish
Schedule performance
0.58
earned ÷ planned value
Next milestone
in 14 days
Build complete
Expand allCollapse all
Activity
Unified Enterprise Network for HQ & the BranchesPlanned: ⁦2025-05-11⁩ → ⁦2027-01-31⁩Forecast: ⁦2025-05-11⁩ → ⁦2027-03-01⁩Float: ⁦0⁩d
Management & governancePlanned: ⁦2025-05-11⁩ → ⁦2025-09-18⁩Actual: ⁦2025-05-11⁩ → ⁦2025-12-08⁩
Project plan & baselinePlanned: ⁦2025-05-11⁩ → ⁦2025-07-30⁩Actual: ⁦2025-05-11⁩ → ⁦2025-09-18⁩
Monitoring & reportingPlanned: ⁦2025-06-30⁩ → ⁦2025-09-18⁩Actual: ⁦2025-07-31⁩ → ⁦2025-12-08⁩
Project plan approvedPlanned: ⁦2025-09-18⁩ → ⁦2025-09-18⁩Actual: ⁦2025-12-08⁩ → ⁦2025-12-08⁩Project plan approved
Design & permitsPlanned: ⁦2025-08-19⁩ → ⁦2025-12-27⁩Actual: ⁦2025-10-20⁩ → ⁦2026-05-19⁩
Detailed designPlanned: ⁦2025-08-19⁩ → ⁦2025-11-07⁩Actual: ⁦2025-10-20⁩ → ⁦2026-02-27⁩
Permits & approvalsPlanned: ⁦2025-10-08⁩ → ⁦2025-12-27⁩Actual: ⁦2026-01-09⁩ → ⁦2026-05-19⁩
Designs approvedPlanned: ⁦2025-12-27⁩ → ⁦2025-12-27⁩Actual: ⁦2026-05-19⁩ → ⁦2026-05-19⁩Designs approved
Civil worksPlanned: ⁦2025-11-27⁩ → ⁦2026-05-26⁩Forecast: ⁦2026-03-07⁩ → ⁦2026-11-11⁩Float: ⁦0⁩d
Site works & excavationPlanned: ⁦2025-11-27⁩ → ⁦2026-02-15⁩Actual: ⁦2026-03-31⁩ → ⁦2026-08-08⁩
StructurePlanned: ⁦2026-01-16⁩ → ⁦2026-04-06⁩Actual: ⁦2026-06-20⁩ → ⁦2026-10-26⁩
FinishesPlanned: ⁦2026-03-07⁩ → ⁦2026-05-26⁩Forecast: ⁦2026-03-07⁩ → ⁦2026-11-11⁩Float: ⁦0⁩dDrag to change its duration+169
Build completePlanned: ⁦2026-05-26⁩ → ⁦2026-05-26⁩Forecast: ⁦2026-11-11⁩ → ⁦2026-11-11⁩Float: ⁦110⁩dDrag to change its datesBuild complete
MEP worksPlanned: ⁦2026-04-26⁩ → ⁦2026-10-23⁩Forecast: ⁦2026-10-28⁩ → ⁦2027-01-16⁩Float: ⁦0⁩d
SupplyPlanned: ⁦2026-04-26⁩ → ⁦2026-07-15⁩Forecast: ⁦2026-10-28⁩ → ⁦2026-12-03⁩Float: ⁦0⁩dDrag to change its dates+141
InstallationPlanned: ⁦2026-06-15⁩ → ⁦2026-09-03⁩Forecast: ⁦2026-11-19⁩ → ⁦2026-12-25⁩Float: ⁦0⁩dDrag to change its dates+113
Testing & commissioningPlanned: ⁦2026-08-04⁩ → ⁦2026-10-23⁩Forecast: ⁦2026-12-11⁩ → ⁦2027-01-16⁩Float: ⁦0⁩dDrag to change its dates+85
Testing & acceptance completePlanned: ⁦2026-10-23⁩ → ⁦2026-10-23⁩Forecast: ⁦2027-01-16⁩ → ⁦2027-01-16⁩Float: ⁦44⁩dDrag to change its datesTesting & acceptance complete
HandoverPlanned: ⁦2026-09-23⁩ → ⁦2027-01-31⁩Forecast: ⁦2027-01-02⁩ → ⁦2027-03-01⁩Float: ⁦0⁩d
Provisional acceptancePlanned: ⁦2026-09-23⁩ → ⁦2026-12-12⁩Forecast: ⁦2027-01-02⁩ → ⁦2027-02-07⁩Float: ⁦0⁩dDrag to change its dates+57
Final acceptancePlanned: ⁦2026-11-12⁩ → ⁦2027-01-31⁩Forecast: ⁦2027-01-24⁩ → ⁦2027-03-01⁩Float: ⁦0⁩dDrag to change its dates+29
Final handoverPlanned: ⁦2027-01-31⁩ → ⁦2027-01-31⁩Forecast: ⁦2027-03-01⁩ → ⁦2027-03-01⁩Float: ⁦0⁩dDrag to change its datesFinal handover
  • Activities (forecast)
  • Baseline
  • Slip past baseline
  • Critical
  • Milestone
  • Phase / element
  • Today

⁦23⁩ rows shown · Data date ⁦2026-10-28⁩

AI schedule analysis

Computed from the current plan: ⁦9⁩ open activities, data date ⁦2026-10-28⁩

Critical-path risk⁦95%⁩ confidence

The critical path runs through ⁦6⁩ activities with no float

Every day lost on this chain is a day lost at launch. No other activity has three weeks of float or less.
Slippage pattern⁦84%⁩ confidence

Milestones slip 101 days on average

Each milestone’s slip in days, in date order; the later ones slip more than the early ones.

81
143
169
85
29
G1G2G3G4G5

The critical chain

In date order, to final acceptance