Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-019At risk4ExecutionConstructionIn progress

New Premium Members Centre & VIP Lounges

Add to watchlist

A full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.

Budget (BAC)

SAR 7.9M

Actual cost

SAR 4.2M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 8.1M

SAR +161K

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-05-02⁩
Hijri
15 Dhuʻl-Qiʻdah 1447 AH
ApprovedCRT-019-04Permits & approvals

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-019
Project
New Premium Members Centre & VIP Lounges
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Member Experience & Business Development Sector
Sponsor
Eng. Sami A. Al-Fraih
Project manager
Eng. Fahad T. Al-Sulami

1The deliverableAuto-filled

DeliverableAuto-filled
Permits & approvals
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Sami A. Al-Fraih
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦7%⁩
DueAuto-filled
⁦2025-12-02⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-019_2.2_v1.pdfV1Eng. Sami A. Al-Fraih⁦2025-12-10⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Badr N. Al-Haqbani
Accepted byAuto-filled
Eng. Sami A. Al-Fraih
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Designs approved
ContractAuto-filled
CTR-2025-023
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentSubmitted—⁦2025-12-10⁩ 11:44
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-12-11⁩ 13:04
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Sami A. Al-FraihProject ownerOn behalf of Badr N. Al-HaqbaniApprovedInspected and accepted against the approved acceptance criteria.⁦2025-12-16⁩ 14:11
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2025-12-18⁩ 14:23
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-12-21⁩ 09:00

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2025-12-11⁩

Inspection & technical acceptance — owner

Eng. Sami A. Al-Fraih

Approved⁦2025-12-16⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2025-12-18⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2025-12-21⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Sami A. Al-Fraih on ⁦2025-12-10⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-12-11⁩ at ⁦13:04⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Badr N. Al-Haqbani · Project owner

    Approved · ⁦2025-12-16⁩ at ⁦14:11⁩ · On behalf of Badr N. Al-Haqbani (Eng. Sami A. Al-Fraih)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2025-12-18⁩ at ⁦14:23⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-12-21⁩ at ⁦09:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-12-10⁩

    PRJ-2026-019_2.2_v1.pdf

    Eng. Sami A. Al-Fraih

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close