PRJ-2026-020Off track4ExecutionConstructionStalled

The Chamber’s Investment Building — Business Tower on King Fahd Road

Remove from watchlist

A 22-storey office tower on chamber-owned land to diversify non-membership revenue; the foundations of axes 12–16 face high groundwater.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 17.3M

Actual cost

SAR 8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 18.2M

SAR +908K

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

The Chamber’s Investment Building — Business Tower on King Fahd Road

PRJ-2026-020 · Investment Department · Strategic · WP-2024-020

StalledOff track4ExecutionProject manager: Eng. Ahmed Y. Asiri · Sponsor: Sarah A. Al-Qarni
Progress
⁦44%⁩ / ⁦55%⁩
SPI · CPI
0.80 · 0.95
Spend
SAR 8M / SAR 17.3M
Estimate at completion
SAR 18.2M

Schedule

⁦11%⁩ behind⁦44%⁩

Planned to date ⁦55%⁩

Forecast finish: 2027-08-031 Rabiʻ I 1449 AH · 64 days late

SPI0.80Schedule performance index · 0.80CPI0.95Cost performance index · 0.95

Health dimensions

Off track

Last update: 2026-10-2413 Jumada I 1448 AH · Up to date

Deliverables

⁦4⁩ of ⁦9⁩ due deliverables accepted on time (⁦44%⁩)

Next milestones

  • Build complete2027-03-091 Shawwal 1448 AH
  • Testing & acceptance complete2027-06-0429 Dhuʻl-Hijjah 1448 AH
  • Final handover2027-08-0128 Safar 1449 AH

Top risks

  • Unforeseen ground conditions and groundwater at the foundations of axes 12 to 1620
  • Pile lengths exceeding contract quantities12

Open impediments

  • Excavation at axis 14 stopped by groundwater · In progress

Decisions and changes waiting

  • CR-2026-010 · Redesign the foundations of axes 12 to 16

Copilot summary

The scope holds 1 project with a budget of SAR 17.3M: 0 on track and 1 red or critical. Weighted progress is 44% against 55% planned, spend SAR 8M, and EAC SAR 18.2M (SAR 0.9M over).

1 project is more than a month behind baseline; the worst: The Chamber’s Investment Building — Business Tower on King Fahd Road (64 days).

Riyadh Chamber of Commerce & Industry · prepared by Eng. Ahmed Y. Asiri in MunjazInternal

Status: Off track ·Project page