Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-020Off track4ExecutionConstructionStalled

The Chamber’s Investment Building — Business Tower on King Fahd Road

Remove from watchlist

A 22-storey office tower on chamber-owned land to diversify non-membership revenue; the foundations of axes 12–16 face high groundwater.

Early warning: ⁦81%⁩ chance of slipping within ⁦60⁩ days

Budget (BAC)

SAR 17.3M

Actual cost

SAR 8M

⁦46%⁩ of budget

Progress

⁦44%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 18.2M

SAR +908K

SPI · CPI

0.80Schedule performance index · 0.800.95Cost performance index · 0.95

Forecast finish

⁦2027-08-03⁩

64 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure5 March 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 April 2024Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 June 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate24 November 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate5 March 2027Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-11-05⁩
Hijri
21 Rabiʻ II 1445 AH
ApprovedDMD-2026-020The Chamber’s Investment Building — Business Tower on King Fahd Road

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-020
Project
The Chamber’s Investment Building — Business Tower on King Fahd Road
Portfolio
New Headquarters & Investment Assets Portfolio
Sector
Investment Department
Sponsor
Sarah A. Al-Qarni
Project manager
Eng. Ahmed Y. Asiri

1The proposalAuto-filled

TitleAuto-filled
The Chamber’s Investment Building — Business Tower on King Fahd Road
Proposed byAuto-filled
Eng. Ahmed Y. Asiri
DepartmentAuto-filled
Assets & Investment Opportunities Unit
Submitted onAuto-filled
⁦2023-11-05⁩
Proposal numberAuto-filled
DMD-2026-020

2Justification

A 22-storey office tower on chamber-owned land to diversify non-membership revenue; the foundations of axes 12–16 face high groundwater.

3Objectives

  1. Financial sustainability
  2. The chamber’s services across Riyadh city and its governorates

Strategic objectives served

  • SO-4.1 — Financial sustainability
  • SO-2.3 — The chamber’s services across Riyadh city and its governorates

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 17.3M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 12.4M
Supervision & consultingSAR 2.4M
Internal teamSAR 1.6M
Contingency reserve (5%)SAR 865K
TotalSAR 17.3M

6Initial risks

RiskLevelProposed response
Unforeseen ground conditions and groundwater at the foundations of axes 12 to 16HighTreated in the risk management plan
Pile lengths exceeding contract quantitiesMediumTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Ahmed Y. AsiriDirector, Construction Projects & BuildingsSubmitted—⁦2023-11-05⁩ 10:31
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2023-11-07⁩ 14:41
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2023-11-08⁩ 09:48
4Portfolio manager reviewTechnical acceptanceEng. Bandar M. Al-ShammariPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-11-12⁩ 10:55
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2023-11-14⁩ 10:07
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2023-11-19⁩ 12:09

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2023-11-07⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2023-11-08⁩

Portfolio manager review

Eng. Bandar M. Al-Shammari

Approved⁦2023-11-12⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2023-11-14⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2023-11-19⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Ahmed Y. Asiri on ⁦2023-11-05⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2023-11-07⁩ at ⁦14:41⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2023-11-08⁩ at ⁦09:48⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Bandar M. Al-Shammari · Portfolio manager

    Approved · ⁦2023-11-12⁩ at ⁦10:55⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2023-11-14⁩ at ⁦10:07⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2023-11-19⁩ at ⁦12:09⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-11-26⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Ahmed Y. Asiri

  2. V1Returned for edit⁦2023-11-05⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Ahmed Y. Asiri

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close