PRJ-2026-025On track4ExecutionConstructionIn progress

Shaqra Branch Rehabilitation

Add to watchlist

Rehabilitating a leased building for the chamber’s Shaqra branch, with a service hall and a training room.

Budget (BAC)

SAR 2.1M

Actual cost

SAR 741K

⁦35%⁩ of budget

Progress

⁦36%⁩Awaiting acceptance ⁦12%⁩

Estimate at completion

SAR 2.1M

SPI · CPI

1.03Schedule performance index · 1.031.02Cost performance index · 1.02

Forecast finish

⁦2027-09-30⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure4 August 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate13 August 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate12 October 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 February 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate4 August 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Shaqra Branch Rehabilitation

PRJ-2026-025 · Member Experience & Business Development Sector · Operational · WP-2025-025

In progressOn track4ExecutionProject manager: Eng. Mishari K. Al-Otaibi · Sponsor: Eng. Sami A. Al-Fraih
Progress
⁦36%⁩ / ⁦35%⁩
SPI · CPI
1.03 · 1.02
Spend
SAR 741K / SAR 2.1M
Estimate at completion
SAR 2.1M

Schedule

⁦1%⁩ ahead⁦36%⁩

Planned to date ⁦35%⁩

Forecast finish: 2027-09-3029 Rabiʻ II 1449 AH · On time

SPI1.03Schedule performance index · 1.03CPI1.02Cost performance index · 1.02

Health dimensions

On track

Last update: 2026-10-2615 Jumada I 1448 AH · Up to date

Deliverables

⁦5⁩ of ⁦6⁩ due deliverables accepted on time (⁦83%⁩)

Next milestones

  • Build complete2027-02-0629 Shaʻban 1448 AH
  • Testing & acceptance complete2027-06-3025 Muharram 1449 AH
  • Final handover2027-10-044 Jumada I 1449 AH

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 2.1M: 1 on track and 0 red or critical. Weighted progress is 36% against 35% planned, spend SAR 0.7M, and EAC SAR 2.1M (SAR 0M under).

No project is more than a month behind baseline.

Riyadh Chamber of Commerce & Industry · prepared by Eng. Mishari K. Al-Otaibi in MunjazInternal

Status: On track ·Project page