Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-027At risk4ExecutionHybridIn progress

Entrepreneurship Fast Track Platform

Add to watchlist

Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.

Budget (BAC)

SAR 320K

Actual cost

SAR 206K

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 327K

SAR +7,000

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Execution

Deliverable completion certificate

Evidence, inspection, acceptance and the financial link

Form no.
RC-PMO-F08
Template edition
1.1
Version
V1
Form date
⁦2026-09-04⁩
Hijri
22 Rabiʻ I 1448 AH
ApprovedCRT-027-05Release 1

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-027
Project
Entrepreneurship Fast Track Platform
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Training & Employment Centre
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Ghada A. Al-Shahrani

1The deliverableAuto-filled

DeliverableAuto-filled
Release 1
DescriptionAuto-filled
A contractual output tied to its WBS work package.
OwnerAuto-filled
Eng. Turki A. Al-Anazi
VersionAuto-filled
V1
Weight in the projectAuto-filled
⁦16%⁩
DueAuto-filled
⁦2026-05-26⁩

2Evidence of completionAuto-filled

FileVersionByDate
PRJ-2026-027_3.1_v1.pdfV1Eng. Turki A. Al-Anazi⁦2026-06-08⁩

3Inspection and acceptance criteria

CriterionResult
Matches the approved scope of workMet
Quality review with no major findingsMet
Evidence attached and signed by the ownerMet
Met3 of 3
InspectorAuto-filled
Eng. Abdulrahman S. Al-Harbi
Accepted byAuto-filled
Eng. Turki A. Al-Anazi
Acceptance note
Inspected and accepted against the approved acceptance criteria.

4Financial linkAuto-filled

Contract milestoneAuto-filled
Build complete
ContractAuto-filled
CTR-2026-001
Payment certificateAuto-filled
Linked when the certificate is raised
Payment against itAuto-filled
—

Approval logChain: Deliverable acceptance & certificate · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreSubmitted—⁦2026-06-08⁩ 11:44
2Evidence against the acceptance criteriaMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2026-06-09⁩ 13:52
3Inspection & technical acceptance — ownerTechnical acceptanceEng. Turki A. Al-AnaziProject ownerOn behalf of Eng. Abdulrahman S. Al-HarbiApprovedInspected and accepted against the approved acceptance criteria.⁦2026-06-14⁩ 14:59
4Deliverable matched to the contract lineFinancial approvalMazen A. Al-HazmiProcurement & contractsApproved—⁦2026-06-16⁩ 14:11
5Certificate linked to the payment certificateFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-06-17⁩ 09:48

Signatures

Evidence against the acceptance criteria

Ghada A. Al-Shahrani

Approved⁦2026-06-09⁩

Inspection & technical acceptance — owner

Eng. Turki A. Al-Anazi

Approved⁦2026-06-14⁩

Deliverable matched to the contract line

Mazen A. Al-Hazmi

Approved⁦2026-06-16⁩

Certificate linked to the payment certificate

Munirah A. Al-Khalidi

Approved⁦2026-06-17⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F08 · version V1

Deliverable completion certificate

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Deliverable acceptance & certificate · version ⁦1⁩

Submitted by Eng. Turki A. Al-Anazi on ⁦2026-06-08⁩

  1. Methodology review

    Evidence against the acceptance criteria

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2026-06-09⁩ at ⁦13:52⁩

  2. Technical acceptance

    Inspection & technical acceptance — owner

    Eng. Abdulrahman S. Al-Harbi · Project owner

    Approved · ⁦2026-06-14⁩ at ⁦14:59⁩ · On behalf of Eng. Abdulrahman S. Al-Harbi (Eng. Turki A. Al-Anazi)

    Inspected and accepted against the approved acceptance criteria.

  3. Financial approval

    Deliverable matched to the contract line

    Mazen A. Al-Hazmi · Procurement & contracts

    On the path because: Contract link?

    Approved · ⁦2026-06-16⁩ at ⁦14:11⁩

  4. Financial approval

    Certificate linked to the payment certificate

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-06-17⁩ at ⁦09:48⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2026-06-08⁩

    PRJ-2026-027_3.1_v1.pdf

    Eng. Turki A. Al-Anazi

Only one version so far.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close