PRJ-2026-027At risk4ExecutionHybridIn progress

Entrepreneurship Fast Track Platform

Add to watchlist

Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.

Budget (BAC)

SAR 320K

Actual cost

SAR 206K

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 327K

SAR +7,000

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

−9

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is behind plan: ⁦63% done against 72% planned⁩.

⁦SPI 0⁩.⁦88⁩, ⁦CPI 0⁩.⁦98⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Partner in GrowthSO-2.4Empower entrepreneurship, SMEs and employment

Main initiative

SI-2.4.2Capability building & entrepreneurship

Contribution to the initiative⁦46%⁩

The project’s share of the initiative’s project budget (2 projects)

Secondary links

No secondary links

Annual work-plan line
WP-2025-027
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦63%⁩

Awaiting acceptance ⁦10%⁩

Not handed in ⁦27%⁩

6 deliverables accepted

  • Release 1⁦16%⁩
  • Release 2⁦16%⁩
  • Business requirements⁦11%⁩
  • Solution design⁦10%⁩
  • Project plan & baseline⁦5%⁩
  • Monitoring & reporting⁦5%⁩

1 deliverable under inspection or acceptance

  • Integrations⁦10%⁩

Progress & earned value

⁦3⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦86%⁩ of budget

206K/ 320K7,000projected overrun(⁦2.2%⁩)
Actual spend
206K
Committed
275K
Approved budget
320K
Estimate at completion
327K

Next milestones

  • Provisional acceptance⁦2026-12-20⁩was ⁦2026-11-27⁩Late
  • Closure⁦2027-01-31⁩was ⁦2026-12-31⁩Late

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

1 open risk, exposure SAR 12.5K

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩1Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩RSK-0040Low uptake of the Fast Track readiness assessment among start-upsProbability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium1
  • Low0

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦6⁩ of ⁦11⁩ approved

  • Project plan & baseline027-D1 · V1 · CRT-027-01⁦5%⁩Ghada A. Al-Shahrani⁦2025-12-30⁩2025-12-3010 Rajab 1447 AHApproved
  • Monitoring & reporting027-D2 · V1 · CRT-027-02⁦5%⁩Eng. Abdulrahman S. Al-Harbi⁦2026-02-05⁩2026-02-0517 Shaʻban 1447 AHApproved
  • Business requirements027-D3 · V1 · CRT-027-03⁦11%⁩Eng. Abdulrahman S. Al-Harbi⁦2026-03-14⁩2026-03-1425 Ramadan 1447 AHApproved
  • Solution design027-D4 · V1 · CRT-027-04⁦10%⁩Eng. Turki A. Al-Anazi⁦2026-04-19⁩2026-04-192 Dhuʻl-Qiʻdah 1447 AHApproved
  • Release 1027-D5 · V1 · CRT-027-05⁦16%⁩Eng. Turki A. Al-Anazi⁦2026-05-26⁩2026-05-269 Dhuʻl-Hijjah 1447 AHApproved
  • Release 2027-D6 · V1 · CRT-027-06⁦16%⁩Ghada A. Al-Shahrani⁦2026-07-01⁩2026-07-0116 Muharram 1448 AHApproved
  • Integrations027-D7 · V1⁦10%⁩Eng. Abdulrahman S. Al-Harbi82 days overdue2026-08-0724 Safar 1448 AHIn review
  • System testing027-D8 · V0⁦8%⁩Ghada A. Al-Shahrani46 days overdue2026-09-121 Rabiʻ II 1448 AHDraft
  • User acceptance testing027-D9 · V0⁦7%⁩Eng. Abdulrahman S. Al-Harbi9 days overdue2026-10-198 Jumada I 1448 AHDraft
  • Training & change027-D10 · V0⁦6%⁩Eng. Abdulrahman S. Al-HarbiIn 27 days2026-11-2414 Jumada II 1448 AHDraft
  • Go-live & handover027-D11 · V0⁦6%⁩Eng. Turki A. Al-AnaziIn 64 days2026-12-3122 Rajab 1448 AHDraft

Team, contracts & documents

Team

4 members

Ghada A. Al-Shahrani · Director, Entrepreneurship & Young BusinesspeopleSarah A. Al-Qarni · Assistant Secretary-General, Support ServicesLama S. Al-Harbi · Senior Business Analyst — Member ServicesNouf M. Al-Balawi · Change Management Specialist
  • Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleProject managerP-029g.alshahrani@chamber.sa⁦50%⁩
  • Sarah A. Al-QarniSarah A. Al-QarniAssistant Secretary-General, Support ServicesFunding and partnership approvalP-012s.alqarni@chamber.sa⁦10%⁩
  • Lama S. Al-HarbiLama S. Al-HarbiSenior Business Analyst — Member ServicesMapping the entrepreneur’s journey on the Fast TrackP-006l.alharbi@chamber.sa⁦15%⁩
  • Nouf M. Al-BalawiNouf M. Al-BalawiChange Management SpecialistEntrepreneur communications planP-035n.albalawi@chamber.sa⁦45%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close