PRJ-2026-027At risk4ExecutionHybridIn progress
Entrepreneurship Fast Track Platform
Add to watchlistReadiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.
Project managerGhada A. Al-ShahraniProject sponsorEng. Turki A. Al-AnaziProgrammeInstitutional Excellence & Capability Programme
Budget (BAC)
SAR 320K
Actual cost
SAR 206K
64% of budget
Progress
63%Awaiting acceptance 10%
Estimate at completion
SAR 327K
SAR +7,000
SPI · CPI
0.88Schedule performance index · 0.880.98Cost performance index · 0.98
Forecast finish
2027-01-31
31 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Periodic update cards
Filled by the project manager every period — progress, status, risks and support requested — prefilled from the previous card and the live data, then approved.
Periodic update cards
| Period | Status | Progress | Current step | Date |
|---|---|---|---|---|
| October 2026UPD-027-2026-10 | Draft | 63% | — | 2026-10-26 |
| September 2026UPD-027-2026-09 | Approved | 60% | — | 2026-10-02 |
| August 2026UPD-027-2026-08 | Approved | 56% | — | 2026-09-02 |