Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-027At risk4ExecutionHybridIn progress

Entrepreneurship Fast Track Platform

Add to watchlist

Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.

Budget (BAC)

SAR 320K

Actual cost

SAR 206K

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 327K

SAR +7,000

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.

In scope

  • Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-11-22⁩

    Baseline approved at the planning gate

    Budget320KFinish⁦2026-12-31⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional2
  • Technical1
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦17%⁩

1/6 · test result is a pass

Accepted

⁦17%⁩

1/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-027-01An end-to-end digital journey, no walk-inBusinessMustIn progressEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saSB-1
REQ-027-02Nafath single sign-onFunctionalMustApprovedGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.saSB-1
REQ-027-03A user dashboardFunctionalMustApprovedEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saSB-1
REQ-027-04Integration with internal systemsTechnicalShouldIn progressGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.saSB-1
REQ-027-05⁦WCAG 2⁩.⁦1⁩ accessibilityRegulatoryShouldIn progressEng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.saSB-1
REQ-027-06Essential cybersecurity controlsSecurityCouldApprovedGhada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.