PRJ-2026-027At risk4ExecutionHybridIn progress

Entrepreneurship Fast Track Platform

Add to watchlist

Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.

Budget (BAC)

SAR 320K

Actual cost

SAR 206K

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 327K

SAR +7,000

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 320K split into spent, committed and left, with the estimate at completion

Forecast overrun SAR 7,000
EAC SAR 327K
Revised request SAR 320K
  • Actual spendSAR 206K
  • Committed, not spentSAR 69K
  • Allotted, uncommittedSAR 35.4K
  • Contingency availableSAR 9,600

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 315K
Original budgetwhen the first baseline was approved
SAR 320K
Approved budgetafter approved change requests
SAR 320K
Current budgetavailable to spend now
SAR 320K
Revised budgetif the pending changes are approved
SAR 320K

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 275K
Contracts1 active contract
SAR 245K
Purchase orders⁦1⁩ order
SAR 30K
Remaining budgetapproved less actual
SAR 114K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 206K
Accrualswork done, not yet invoiced
SAR 8,000
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 327K
ContingencySAR 6,400 drawn of SAR 16K
SAR 9,600

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 315K
ApprovedSAR 320K
Estimate at completionSAR 327K
Approved is SAR 5,000 (⁦1.6%⁩) above the estimate
The estimate at completion is SAR 12K (⁦3.8%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-08-19⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51027
  • WBS elements⁦5⁩ elements · P-2026-027.01 …
  • Purchase orders⁦1⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦6⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 6,400 drawn of SAR 16K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 6,400

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.020.030.030.03⁦−0.00⁩
2Analysis & design0.050.060.060.06⁦−0.00⁩
3Build0.120.120.120.12⁦−0.00⁩
4Testing & acceptance0.060.040.000.07⁦−0.00⁩
5Launch & handover0.050.030.000.05⁦−0.00⁩
Unallocated contingency0.010.000.000.01⁦+0.00⁩
Total0.320.280.210.33⁦−0.01⁩

Budget split

WBS

SAR 320K

Budget

  • Management & governanceSAR 24.8K⁦8%⁩
  • Analysis & designSAR 52.8K⁦16%⁩
  • BuildSAR 124.2K⁦39%⁩
  • Testing & acceptanceSAR 62.1K⁦19%⁩
  • Launch & handoverSAR 46.6K⁦15%⁩
  • Unallocated contingencySAR 9,600⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-07-12⁩+193

SPI(t) ⁦0.69⁩ against the approved finish ⁦2026-12-31⁩

Planned valuePV
SAR 302K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 202K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 206K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 320K
The approved budget for the whole project.
BAC
Cost varianceCV
⁦−0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.10⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
0.98
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.67
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 327K
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 121K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦−0.01⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.04
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 326.3K
  • If the rest goes to planSAR 324K
  • At cost and schedule performanceSAR 385.9K
  • The PM’s bottom-up estimateSAR 327K
  • To stay within SAR 320K, cost performance on the rest must rise to ⁦1.04⁩ — above what has been achieved.

Estimate at completion at that performance

SAR 326.4K

Variance at completion: ⁦−0.01⁩ SAR M