PRJ-2026-027At risk4ExecutionHybridIn progress

Entrepreneurship Fast Track Platform

Add to watchlist

Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.

Budget (BAC)

SAR 320K

Actual cost

SAR 206K

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 327K

SAR +7,000

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work310.4K⁦16⁩ elements
Unallocated contingency9,600SAR 16K
Budget at completion320KPRJ-2026-027
Weighted progress⁦63%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project454⁦2025-11-02⁩⁦2027-01-30⁩⁦63%⁩0.310.21—
1
Phase142⁦2025-11-02⁩⁦2026-03-24⁩⁦100%⁩0.020.03—
1.1
WBS element87⁦2025-11-02⁩⁦2026-01-28⁩⁦100%⁩0.010.010 / 1
1.2
WBS element87⁦2025-12-27⁩⁦2026-03-24⁩⁦100%⁩0.010.011 / 2
2
Phase142⁦2026-02-19⁩⁦2026-07-11⁩⁦100%⁩0.050.06—
2.1
WBS element88⁦2026-02-19⁩⁦2026-05-18⁩⁦100%⁩0.030.031 / 1
2.2
WBS element87⁦2026-04-15⁩⁦2026-07-11⁩⁦100%⁩0.030.031 / 2
3
Phase156⁦2026-06-08⁩⁦2026-11-11⁩⁦95%⁩0.120.12—
3.1
WBS element88⁦2026-06-08⁩⁦2026-09-04⁩⁦100%⁩0.040.041 / 1
3.2
WBS element85⁦2026-08-02⁩⁦2026-10-26⁩⁦100%⁩0.040.041 / 1
3.3
WBS element155⁦2026-06-09⁩⁦2026-11-11⁩⁦85%⁩0.040.041 / 2
4
Phase52⁦2026-10-30⁩⁦2026-12-21⁩⁦0%⁩0.06——
4.1
WBS element32⁦2026-10-30⁩⁦2026-12-01⁩⁦0%⁩0.03—1 / 1
4.2
WBS element32⁦2026-11-19⁩⁦2026-12-21⁩⁦0%⁩0.03—1 / 2
5
Phase52⁦2026-12-09⁩⁦2027-01-30⁩⁦0%⁩0.05——
5.1
WBS element32⁦2026-12-09⁩⁦2027-01-10⁩⁦0%⁩0.02—1 / 1
5.2
WBS element32⁦2026-12-29⁩⁦2027-01-30⁩⁦0%⁩0.02—1 / 1
Total⁦63%⁩0.310.21