PRJ-2026-027At risk4ExecutionHybridIn progress

Entrepreneurship Fast Track Platform

Add to watchlist

Readiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.

Budget (BAC)

SAR 320K

Actual cost

SAR 206K

⁦64%⁩ of budget

Progress

⁦63%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 327K

SAR +7,000

SPI · CPI

0.88Schedule performance index · 0.880.98Cost performance index · 0.98

Forecast finish

⁦2027-01-31⁩

31 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure27 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Planning

Kick-off meeting minutes

Roles, tasks, decisions and the start of execution

Form no.
RC-PMO-F06
Template edition
1.2
Version
V1
Form date
⁦2025-11-09⁩
Hijri
18 Jumada I 1447 AH
ApprovedMTG-KO-027Kick-off — Entrepreneurship Fast Track Platform

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-027
Project
Entrepreneurship Fast Track Platform
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Training & Employment Centre
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Ghada A. Al-Shahrani

1The meetingAuto-filled

MeetingAuto-filled
Kick-off — Entrepreneurship Fast Track Platform
Date and timeAuto-filled
⁦2025-11-09⁩ · 10:00
PlaceAuto-filled
Main meeting room — headquarters
SecretaryAuto-filled
Ghada A. Al-Shahrani

Purpose

Project kick-off: confirm the roles, the first tasks and the start decisions, and confirm execution starts per the approved charter.

AttendeesTitle
Eng. Turki A. Al-AnaziExecutive Director, Training & Employment Centre
Eng. Abdulrahman S. Al-HarbiDirector General, Training & Entrepreneurship
Ghada A. Al-ShahraniDirector, Entrepreneurship & Young Businesspeople
Dr. Noura M. Al-OtaibiDirector, Project Management Office
Sarah A. Al-QarniAssistant Secretary-General, Support Services
Lama S. Al-HarbiSenior Business Analyst — Member Services
Nouf M. Al-BalawiChange Management Specialist

2Roles

PersonRoleDuty
Eng. Turki A. Al-AnaziProject sponsorSponsors the project, decides escalations and material changes
Eng. Abdulrahman S. Al-HarbiProject ownerApproves the requirements and accepts the deliverables
Ghada A. Al-ShahraniProject managerRuns the plan, deliverables and risks; files the periodic update card
Dr. Noura M. Al-OtaibiProject Management OfficeFollows the methodology and checks the periodic updates
Sarah A. Al-QarniFunding and partnership approvalDelivers their tasks and uploads the evidence
Lama S. Al-HarbiMapping the entrepreneur’s journey on the Fast TrackDelivers their tasks and uploads the evidence
Nouf M. Al-BalawiEntrepreneur communications planDelivers their tasks and uploads the evidence

3Tasks

TaskOwnerDueStatus
Project plan approvedGhada A. Al-Shahrani⁦2026-02-05⁩Done
Designs approvedGhada A. Al-Shahrani⁦2026-04-19⁩Done
Build completeGhada A. Al-Shahrani⁦2026-08-07⁩Open
Testing & acceptance completeGhada A. Al-Shahrani⁦2026-10-19⁩Open

4Decisions

  1. The charter is the reference for scope, budget and the milestone plan
  2. Change Committee: Approves scope, cost and schedule changes (Weekly)
  3. PMO Committee: Methodology compliance, data quality, stage gates (Fortnightly)
  4. The periodic update card monthly, before the 5th of the month

5Start of execution

Execution starts on
⁦2026-01-09⁩
Start confirmed
Eng. Turki A. Al-Anazi · ⁦2025-11-10⁩

Approval logChain: Kick-off minutes approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleSubmitted—⁦2025-11-10⁩ 14:17
2Chair’s approval (sponsor)Technical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2025-11-11⁩ 12:30
3Minutes against the templateMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2025-11-12⁩ 12:51

Signatures

Minutes against the template

Ghada A. Al-Shahrani

Approved⁦2025-11-12⁩

Chair’s approval (sponsor)

Eng. Turki A. Al-Anazi

Approved⁦2025-11-11⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F06 · version V1

Kick-off meeting minutes

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Kick-off minutes approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2025-11-10⁩

  1. Methodology review

    Minutes against the template

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2025-11-12⁩ at ⁦12:51⁩

  2. Technical acceptance

    Chair’s approval (sponsor)

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2025-11-11⁩ at ⁦12:30⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V1ApprovedCurrent⁦2025-11-09⁩

    The minutes as taken

    Ghada A. Al-Shahrani

Only one version so far.