PRJ-2026-029On track3PlanningWaterfallNot started

Training Centre e-Learning Platform

Add to watchlist

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

Budget (BAC)

SAR 375K

Actual cost

SAR 15K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 375K

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2026-08-14⁩
Hijri
1 Rabiʻ I 1448 AH
ApprovedPRJ-2026-029Training Centre e-Learning Platform

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-029
Project
Training Centre e-Learning Platform
Portfolio
Institutional Excellence & Capability Portfolio
Sector
Training & Employment Centre
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Ghada A. Al-Shahrani

1Objective

Background

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

Project objectives

  1. Empower entrepreneurship, SMEs and employment
  2. Innovative, results-driven human capital

2Scope

In scope

  • A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.
  • Service procedure manual
  • Beneficiary satisfaction measures

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2026-09-05⁩
Main deliverable — stage 1⁦2027-04-29⁩
Main deliverable — final stage⁦2027-10-22⁩
Final report⁦2027-12-31⁩
MilestoneDate
Charter approved⁦2026-08-14⁩
Contract signed⁦2026-11-04⁩
50% of works complete⁦2027-04-29⁩
Provisional acceptance⁦2027-11-21⁩
Closure⁦2027-12-31⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Turki A. Al-Anazi
Project ownerAuto-filled
Eng. Abdulrahman S. Al-Harbi
Project managerAuto-filled
Ghada A. Al-Shahrani
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 270K
Supervision & consultingSAR 50K
Internal teamSAR 35K
Contingency reserve (5%)SAR 20K
Approved budgetSAR 375K

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Ghada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleSubmitted—⁦2026-08-05⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2026-08-08⁩ 12:30
3Project ownerTechnical acceptanceEng. Abdulrahman S. Al-HarbiProject ownerApproved—⁦2026-08-11⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2026-08-12⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Turki A. Al-AnaziProject sponsorApproved—⁦2026-08-14⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2026-08-08⁩

Project owner

Eng. Abdulrahman S. Al-Harbi

Approved⁦2026-08-11⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2026-08-12⁩

Sponsor approval

Eng. Turki A. Al-Anazi

Approved⁦2026-08-14⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Ghada A. Al-Shahrani on ⁦2026-08-05⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2026-08-08⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Eng. Abdulrahman S. Al-Harbi · Project owner

    Approved · ⁦2026-08-11⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2026-08-12⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Turki A. Al-Anazi · Project sponsor

    Approved · ⁦2026-08-14⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2026-08-14⁩

    Approved version

    • PMO comments addressed

    Ghada A. Al-Shahrani

  2. V1Returned for edit⁦2026-07-26⁩

    First draft

    • Returned to detail the budget

    Ghada A. Al-Shahrani