PRJ-2026-029On track3PlanningWaterfallNot started

Training Centre e-Learning Platform

Add to watchlist

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

Budget (BAC)

SAR 375K

Actual cost

SAR 15K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 375K

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 375K split into spent, committed and left, with the estimate at completion

EAC SAR 375K
Revised request SAR 375K
  • Actual spendSAR 15K
  • Committed, not spentSAR 30K
  • Allotted, uncommittedSAR 318.8K
  • Contingency availableSAR 11.3K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 375K
Original budgetwhen the first baseline was approved
SAR 375K
Approved budgetafter approved change requests
SAR 375K
Current budgetavailable to spend now
SAR 375K
Revised budgetif the pending changes are approved
SAR 375K

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 45K
Contracts0 active contracts
SAR 0
Purchase orders⁦1⁩ order
SAR 45K
Remaining budgetapproved less actual
SAR 360K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 15K
Accrualswork done, not yet invoiced
SAR 1,000
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 375K
ContingencySAR 7,750 drawn of SAR 19K
SAR 11.3K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 375K
ApprovedSAR 375K
Estimate at completionSAR 375K
Approved equals the estimate
The estimate at completion is SAR 0 (⁦0.0%⁩) below the estimate

From proposal DMD-2026-006 in the annual work plan — its estimated cost

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-51029
  • WBS elements⁦5⁩ elements · P-2026-029.01 …
  • Purchase orders⁦1⁩ synced · ⁦0⁩ manual
  • Invoices & certificatesNo certificates
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 7,750 drawn of SAR 19K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 7,750

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.030.020.020.03⁦+0.00⁩
2Analysis & design0.060.010.000.06⁦−0.00⁩
3Build0.150.010.000.15⁦−0.00⁩
4Testing & acceptance0.070.010.000.07⁦−0.00⁩
5Launch & handover0.050.010.000.06⁦−0.00⁩
Unallocated contingency0.010.000.000.01⁦+0.01⁩
Total0.380.050.020.38⁦+0.00⁩

Budget split

WBS

SAR 375K

Budget

  • Management & governanceSAR 29.1K⁦8%⁩
  • Analysis & designSAR 61.8K⁦16%⁩
  • BuildSAR 145.5K⁦39%⁩
  • Testing & acceptanceSAR 72.8K⁦19%⁩
  • Launch & handoverSAR 54.6K⁦15%⁩
  • Unallocated contingencySAR 11.3K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative
  • Forecast

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2028-08-16⁩+229

SPI(t) ⁦0.69⁩ against the approved finish ⁦2027-12-31⁩

Planned valuePV
SAR 31K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 15K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 15K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 375K
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.00⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.02⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.00
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.48
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 375K
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 360K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.00⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
1.00
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 375K
  • If the rest goes to planSAR 375K
  • At cost and schedule performanceSAR 759K
  • The PM’s bottom-up estimateSAR 375K
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 375K

Variance at completion: ⁦+0.00⁩ SAR M