PRJ-2026-029On track3PlanningWaterfallNot started

Training Centre e-Learning Platform

Add to watchlist

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

Budget (BAC)

SAR 375K

Actual cost

SAR 15K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 375K

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Fields required by the project’s stage (Planning): 15 fields required now.Field settings

Auto-filled from the approved proposal

5 sections were filled from the project proposal & feasibility study approved at the first gate — review and edit if needed. — DMD-2026-006 · Training centre e-learning platform

Riyadh Chamber of Commerce & Industry

Project charter

Training Centre e-Learning Platform

APPROVEDV2Approved ⁦2026-08-14⁩

1Project identity

Required at this stage
Project name
Training Centre e-Learning Platform
Project code
PRJ-2026-029
Project sponsor
Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa
Project manager
Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa
Project owner
Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa
Portfolio & programme
Institutional Excellence & Capability PortfolioInstitutional Excellence & Capability Programme
Type & methodology
Service · Waterfall
Current phase
3Planning

2Background & rationale

Auto-filled from project proposal DMD-2026-006Required at this stage

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

3Objectives

Auto-filled from project proposal DMD-2026-006Required at this stage
  1. 1Empower entrepreneurship, SMEs and employment
  2. 2Innovative, results-driven human capital

4Scope

Required at this stage

In scope

  • A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.
  • Service procedure manual
  • Beneficiary satisfaction measures

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Service procedure manual
  2. 2Beneficiary satisfaction measures
  3. 3Training for service staff

6Deliverables

Required at this stage
1Project management plan⁦2026-09-05⁩
2Main deliverable — stage 1⁦2027-04-29⁩
3Main deliverable — final stage⁦2027-10-22⁩
4Final report⁦2027-12-31⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2026-08-14⁩
  2. Contract signed⁦2026-11-04⁩
  3. 50% of works complete⁦2027-04-29⁩
  4. Provisional acceptance⁦2027-11-21⁩
  5. Closure⁦2027-12-31⁩
  • Main contract⁦72.0%⁩270K
  • Supervision & consulting⁦13.3%⁩50K
  • Internal team⁦9.3%⁩35K
  • Contingency reserve (⁦5%⁩)⁦5.3%⁩20K
The owning sector’s approved budgetTotal375K

9Timeline

Required at this stage
Start
2026-08-163 Rabiʻ I 1448 AH
Baseline finish
2027-12-313 Shaʻban 1449 AH
Duration
⁦17⁩ months

10Key risks

Auto-filled from project proposal DMD-2026-006Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Auto-filled from project proposal DMD-2026-006Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly