Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-029On track3PlanningWaterfallNot started

Training Centre e-Learning Platform

Add to watchlist

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

Budget (BAC)

SAR 375K

Actual cost

SAR 15K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 375K

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+6

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦4% done against 4% planned⁩.

⁦SPI 1⁩.⁦00⁩, ⁦CPI 1⁩.⁦00⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Partner in GrowthSO-2.4Empower entrepreneurship, SMEs and employment

Main initiative

SI-2.4.2Capability building & entrepreneurship

Contribution to the initiative⁦54%⁩

The project’s share of the initiative’s project budget (2 projects)

Annual work-plan line
WP-2026-029
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦4%⁩

Awaiting acceptance ⁦0%⁩

Not handed in ⁦96%⁩

1 deliverable accepted

  • Project plan & baseline⁦4%⁩

0 deliverables under inspection or acceptance

    Progress & earned value

    ⁦1⁩ of ⁦5⁩ milestones complete

    Earned-value curve

    Planned, earned and actual to the data date, cumulative, with the forecast cost tail

    • Planned value
    • Earned value
    • Actual cost
    • Estimate at completion
    • Budget at completion

    Budget & commitments

    Commitments are ⁦12%⁩ of budget

    15K/ 375K
    Actual spend
    15K
    Committed
    45K
    Approved budget
    375K
    Estimate at completion
    375K

    Next milestones

    • Contract signed⁦2026-11-04⁩On track
    • 50% of works complete⁦2027-04-29⁩On track
    • Provisional acceptance⁦2027-11-21⁩On track
    • Closure⁦2027-12-31⁩On track

    Waiting on someone

    ⁦0⁩ approvals and ⁦0⁩ open actions on this project

    Approvals & requests

    From «My actions» for this project

    • No approvals pending

    Actions

    ⁦0⁩ open

    • No actions on this project

    Change requests

    Cost and schedule impact

    • No change requests

    Risks & impediments

    0 open risks, exposure SAR 0

    Risk map

    Probability
    5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
    4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
    3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
    2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
    1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
    12345

    Impact

    • Critical0
    • High0
    • Medium0
    • Low0

    Top risks

    • No open risks

    Open impediments

    ⁦0⁩ escalated

    • No open impediments

    Deliverables

    ⁦1⁩ of ⁦11⁩ approved

    • Project plan & baseline029-D1 · V1 · CRT-029-01⁦4%⁩Ghada A. Al-Shahrani⁦2026-10-24⁩2026-10-2413 Jumada I 1448 AHApproved
    • Monitoring & reporting029-D2 · V0⁦4%⁩Eng. Abdulrahman S. Al-HarbiIn 40 days2026-12-0727 Jumada II 1448 AHDraft
    • Business requirements029-D3 · V0⁦9%⁩Eng. Abdulrahman S. Al-HarbiIn 83 days2027-01-1911 Shaʻban 1448 AHDraft
    • Solution design029-D4 · V0⁦9%⁩Eng. Turki A. Al-AnaziIn 126 days2027-03-0324 Ramadan 1448 AHDraft
    • Release 1029-D5 · V0⁦13%⁩Eng. Turki A. Al-AnaziIn 169 days2027-04-158 Dhuʻl-Qiʻdah 1448 AHDraft
    • Release 2029-D6 · V0⁦13%⁩Ghada A. Al-ShahraniIn 213 days2027-05-2923 Dhuʻl-Hijjah 1448 AHDraft
    • Integrations029-D7 · V0⁦13%⁩Eng. Abdulrahman S. Al-HarbiIn 256 days2027-07-117 Safar 1449 AHDraft
    • System testing029-D8 · V0⁦10%⁩Ghada A. Al-ShahraniIn 299 days2027-08-2321 Rabiʻ I 1449 AHDraft
    • User acceptance testing029-D9 · V0⁦10%⁩Eng. Abdulrahman S. Al-HarbiIn 342 days2027-10-055 Jumada I 1449 AHDraft
    • Training & change029-D10 · V0⁦8%⁩Eng. Abdulrahman S. Al-HarbiIn 386 days2027-11-1819 Jumada II 1449 AHDraft
    • Go-live & handover029-D11 · V0⁦7%⁩Eng. Turki A. Al-AnaziIn 429 days2027-12-313 Shaʻban 1449 AHDraft

    Team, contracts & documents

    Team

    2 members

    Ghada A. Al-Shahrani · Director, Entrepreneurship & Young BusinesspeopleAbdulmajeed R. Al-Dosari · Director General, Human Resources
    • Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleProject managerP-029g.alshahrani@chamber.sa⁦35%⁩
    • Abdulmajeed R. Al-DosariAbdulmajeed R. Al-DosariDirector General, Human ResourcesChamber staff development tracks on the platformP-019am.aldosari@chamber.sa⁦15%⁩

    Contracts

    0 contracts

    • No external contracts — delivered in-house

    Documents

    • No documents yet

    Meetings

    • No meetings scheduled
    Esc

    Quick actions

    Go to

    Projects

    ↑↓to move↵to openEscto close