Training Centre e-Learning Platform
Add to watchlistA learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.
Budget (BAC)
Actual cost
4% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
PlanningStage 3 of 5
Next gate:Execution4 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
- Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
- Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-12-07 | 2027-01-05 | +29 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | At risk | 0 | Not requested |
| Designs approvedMS-G2 | Project | 2027-03-03 | 2027-04-01 | +29 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | At risk | 0 | Not requested |
| Build completeMS-G3 | Contractual | 2027-07-11 | 2027-08-08 | +28 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | At risk | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2027-10-05 | 2027-11-02 | +28 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | At risk | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2027-12-31 | 2028-01-27 | +27 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
4%Awaiting acceptance
0%Not handed in
96%Deliverable flow
Display options
| Project plan & baseline029-D1 | 4% | CRT-029-01 | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-10-24 | V1 | 3 of 3 |
| Monitoring & reporting029-D2 | 4% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-12-07 | V0 | 0 of 3 |
| Business requirements029-D3 | 9% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-01-19 | V0 | 0 of 3 |
| Solution design029-D4 | 9% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-03-03 | V0 | 0 of 3 |
| Release 1029-D5 | 13% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-04-15 | V0 | 0 of 3 |
| Release 2029-D6 | 13% | — | Draft | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-05-29 | V0 | 0 of 3 |
| Integrations029-D7 | 13% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-07-11 | V0 | 0 of 3 |
| System testing029-D8 | 10% | — | Draft | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-08-23 | V0 | 0 of 3 |
| User acceptance testing029-D9 | 10% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-10-05 | V0 | 0 of 3 |
| Training & change029-D10 | 8% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-11-18 | V0 | 0 of 3 |
| Go-live & handover029-D11 | 7% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2027-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |