Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 3
- Date
- 2025-09-16
- Hijri
- 24 Rabiʻ I 1447 AH
- Reference
- PAY-2025-005-03
Interim payment certificate no. (3)
For the work of August 2025
- Contract number
- RC/2025/005
- Supplier-portal reference
- 2503460459
- Contract
- Solar PV supply & installation — chamber buildings & branches
- Contractor
- Sustainable Energy Contracting Est.
- Contractor VAT number
- 335500417280003
- Project
- Solar Power for the Chamber’s Buildings & Branches
- Contract period
- 2025-04-06 — 2027-04-30
- Original contract value
- 4,050,000
- Current contract value
- 4,050,000
- Linked milestone
- Earthworks & foundations complete · MS-G2 Designs approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 547,500 |
| 2 | Less: previous certificates | (322,000) |
| 3 | Value of work in this certificate | 225,500 |
| 4 | Less: retention (10%) | (22,550) |
| 5 | Less: advance payment recovery (10%) | (22,550) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (45,100) |
| 8 | Net before VAT | 180,400 |
| 9 | Add: value added tax (15%) | 27,060 |
| 10 | Net amount payable to the contractor | 207,460 |
Amount in words: Two hundred seven thousand four hundred sixty Saudi riyals only
Retention held up to this certificate: SAR 54.8K — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Preliminaries & mobilisation | 283,500 | 53,300 | 35,100 | 88,400 | 31% |
| Earthworks & foundations | 729,000 | 82,600 | 55,350 | 137,950 | 19% |
| Concrete & structural works | 1,255,500 | 109,650 | 77,050 | 186,700 | 15% |
| Mechanical, electrical & plumbing | 972,000 | 52,600 | 39,400 | 92,000 | 9% |
| Finishes & external works | 607,500 | 20,800 | 16,150 | 36,950 | 6% |
| Testing & commissioning | 202,500 | 3,050 | 2,450 | 5,500 | 3% |
| Total | 4,050,000 | 322,000 | 225,500 | 547,500 | 14% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Eng. Abdulelah M. Al-Anazi
Supervising engineer
Eng. Ibrahim A. Al-Ghamdi
Project manager
Eng. Mishari K. Al-Otaibi
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Dr. Abdullah S. Al-Qahtani