Kingdom of Saudi Arabia
Riyadh Chamber of Commerce & Industry
General Directorate of Finance & Procurement — Contracts & Procurement Department
- Certificate no.
- 2
- Date
- 2025-08-30
- Hijri
- 7 Rabiʻ I 1447 AH
- Reference
- PAY-2025-010-02
Interim payment certificate no. (2)
For the work of August 2025
- Contract number
- RC/2025/010
- Supplier-portal reference
- 2503810524
- Contract
- Dispute settlement & arbitration platform Release 2 development
- Contractor
- Digital Platforms Solutions Co.
- Contractor VAT number
- 310105738640003
- Project
- Dispute Settlement & Commercial Arbitration Platform — Release 2
- Contract period
- 2025-06-01 — 2026-11-30
- Original contract value
- 740,000
- Current contract value
- 740,000
- Linked milestone
- Design approved · MS-G1 Project plan approved
Certificate summary (SAR)
| 1 | Total value of work completed to date | 75,500 |
| 2 | Less: previous certificates | (28,500) |
| 3 | Value of work in this certificate | 47,000 |
| 4 | Less: retention (5%) | (2,350) |
| 5 | Less: advance payment recovery (10%) | (4,700) |
| 6 | Less: delay and breach penalties | 0 |
| 7 | Total deductions | (7,050) |
| 8 | Net before VAT | 39,950 |
| 9 | Add: value added tax (15%) | 5,993 |
| 10 | Net amount payable to the contractor | 45,943 |
Amount in words: Forty-five thousand nine hundred forty-three Saudi riyals only
Retention held up to this certificate: SAR 3,775 — released after final acceptance.
Work by contract item
| Item | Item value | Previous | This period | To date | Complete |
|---|---|---|---|---|---|
| Analysis & design | 111,000 | 6,550 | 10,050 | 16,600 | 15% |
| Licences & platform | 148,000 | 7,550 | 12,100 | 19,650 | 13% |
| Build & configuration | 222,000 | 8,450 | 14,200 | 22,650 | 10% |
| Systems integration | 111,000 | 3,300 | 5,750 | 9,050 | 8% |
| Testing & acceptance | 74,000 | 1,600 | 2,950 | 4,550 | 6% |
| Training & run | 74,000 | 1,050 | 1,950 | 3,000 | 4% |
| Total | 740,000 | 28,500 | 47,000 | 75,500 | 10% |
Amounts in Saudi riyals.
Signatures and approvals
Contractor’s representative
Rayan M. Al-Shehri
Supervising engineer
Hussam T. Al-Qurashi
Project manager
Karim Haddad
Finance & contracts
Khalid N. Al-Mutairi
Final approver
Munirah A. Al-Khalidi