RC/2025/010
Terms, guarantees, milestones, variation orders and payment certificates.
From original to current value
The original value and each approved variation
85% of the current value paid
Paid
630Kof a current value of SAR 740K
Value of each certificate
The last 11 — gross and net
Approved: 11
Count: 11 · in the approval chain: 0
| Certificate | Submitted | Gross | Retention | Deductions | VAT | Net | Status | |
|---|---|---|---|---|---|---|---|---|
| Certificate 11September 2026 | 2026-10-06 | 28K | 1,400 | 2,800 | 3,570 | 27.4K | Approved | |
| Certificate 10August 2026 | 2026-08-22 | 48K | 2,400 | 4,800 | 6,120 | 46.9K | Approved | |
| Certificate 9June 2026 | 2026-07-09 | 55.5K | 2,775 | 5,550 | 7,076 | 54.3K | Approved | |
| Certificate 8May 2026 | 2026-05-25 | 66K | 3,300 | 6,600 | 8,415 | 64.5K | Approved | |
| Certificate 7March 2026 | 2026-04-10 | 83.5K | 4,175 | 8,350 | 10.6K | 81.6K | Approved | |
| Certificate 6February 2026 | 2026-02-25 | 70.5K | 3,525 | 7,050 | 8,989 | 68.9K | Approved | |
| Certificate 5December 2025 | 2026-01-11 | 77.5K | 3,875 | 7,750 | 9,881 | 75.8K | Approved | |
| Certificate 4November 2025 | 2025-11-27 | 73K | 3,650 | 7,300 | 9,308 | 71.4K | Approved | |
| Certificate 3September 2025 | 2025-10-13 | 52.5K | 2,625 | 5,250 | 6,694 | 51.3K | Approved | |
| Certificate 2August 2025 | 2025-08-30 | 47K | 2,350 | 4,700 | 5,993 | 45.9K | Approved | |
| Certificate 1June 2025 | 2025-07-16 | 28.5K | 1,425 | 2,850 | 3,634 | 27.9K | Approved |