PRJ-2026-008On track4ExecutionScrumIn progress

Dispute Settlement & Commercial Arbitration Platform — Release 2

Add to watchlist

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Budget (BAC)

SAR 920K

Actual cost

SAR 821K

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 902K

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project health across eight dimensions

A weighted index, not just percent complete; each dimension leads to the tab that explains it.

Index over the last six reports

+3

May to October 2026

No material change in the health dimensions over the period.

Copilot summary

Generated from the live project data

The project is close to plan: ⁦91% done against 90% planned⁩.

⁦SPI 1⁩.⁦01⁩, ⁦CPI 1⁩.⁦02⁩.

The project’s link, progress and status

How the project ties to the strategy, its progress counted from accepted deliverables, and its status history.

Strategic link

The main objective and initiative, the secondary links, and the project’s contribution to its initiative.

Main strategic objective· Axis: A Partner in GrowthSO-2.1High-quality, value-adding digital core services for members

Main initiative

SI-2.1.2Dispute settlement & commercial arbitration

Contribution to the initiative⁦100%⁩

The project’s share of the initiative’s project budget (1 project)

Secondary links

Annual work-plan line
WP-2025-008
Classification
Strategic

Project progress from accepted deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate; nothing counts before acceptance.

Counted

⁦91%⁩

Awaiting acceptance ⁦5%⁩

Not handed in ⁦4%⁩

9 deliverables accepted

  • Release 1⁦14%⁩
  • Release 2⁦14%⁩
  • Integrations⁦14%⁩
  • System testing⁦11%⁩
  • User acceptance testing⁦11%⁩
  • Business requirements⁦9%⁩
  • Solution design⁦9%⁩
  • Project plan & baseline⁦5%⁩

1 deliverable under inspection or acceptance

  • Training & change⁦5%⁩

Progress & earned value

⁦4⁩ of ⁦5⁩ milestones complete

Earned-value curve

Planned, earned and actual to the data date, cumulative, with the forecast cost tail

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Budget & commitments

Commitments are ⁦92%⁩ of budget

821K/ 920K18Kprojected saving(⁦2.0%⁩)
Actual spend
821K
Committed
845K
Approved budget
920K
Estimate at completion
902K

Next milestones

  • Closure⁦2026-11-26⁩was ⁦2026-11-30⁩On track

Waiting on someone

⁦0⁩ approvals and ⁦0⁩ open actions on this project

Approvals & requests

From «My actions» for this project

  • No approvals pending

Actions

⁦0⁩ open

  • No actions on this project

Change requests

Cost and schedule impact

  • No change requests

Risks & impediments

0 open risks, exposure SAR 0

Risk map

Probability
5Probability: Almost certain · Impact: NegligibleLow · Score ⁦5⁩Probability: Almost certain · Impact: MinorMedium · Score ⁦10⁩Probability: Almost certain · Impact: ModerateHigh · Score ⁦15⁩Probability: Almost certain · Impact: MajorCritical · Score ⁦20⁩Probability: Almost certain · Impact: SevereCritical · Score ⁦25⁩
4Probability: Likely · Impact: NegligibleLow · Score ⁦4⁩Probability: Likely · Impact: MinorMedium · Score ⁦8⁩Probability: Likely · Impact: ModerateMedium · Score ⁦12⁩Probability: Likely · Impact: MajorHigh · Score ⁦16⁩Probability: Likely · Impact: SevereCritical · Score ⁦20⁩
3Probability: Possible · Impact: NegligibleLow · Score ⁦3⁩Probability: Possible · Impact: MinorLow · Score ⁦6⁩Probability: Possible · Impact: ModerateMedium · Score ⁦9⁩Probability: Possible · Impact: MajorMedium · Score ⁦12⁩Probability: Possible · Impact: SevereHigh · Score ⁦15⁩
2Probability: Unlikely · Impact: NegligibleLow · Score ⁦2⁩Probability: Unlikely · Impact: MinorLow · Score ⁦4⁩Probability: Unlikely · Impact: ModerateLow · Score ⁦6⁩Probability: Unlikely · Impact: MajorMedium · Score ⁦8⁩Probability: Unlikely · Impact: SevereMedium · Score ⁦10⁩
1Probability: Rare · Impact: NegligibleLow · Score ⁦1⁩Probability: Rare · Impact: MinorLow · Score ⁦2⁩Probability: Rare · Impact: ModerateLow · Score ⁦3⁩Probability: Rare · Impact: MajorLow · Score ⁦4⁩Probability: Rare · Impact: SevereLow · Score ⁦5⁩
12345

Impact

  • Critical0
  • High0
  • Medium0
  • Low0

Top risks

  • No open risks

Open impediments

⁦0⁩ escalated

  • No open impediments

Deliverables

⁦9⁩ of ⁦11⁩ approved

  • Project plan & baseline008-D1 · V1 · CRT-008-01⁦5%⁩Karim Haddad⁦2025-07-22⁩2025-07-2227 Muharram 1447 AHApproved
  • Monitoring & reporting008-D2 · V1 · CRT-008-02⁦4%⁩Dr. Lina S. Al-Hazzani⁦2025-09-10⁩2025-09-1018 Rabiʻ I 1447 AHApproved
  • Business requirements008-D3 · V1 · CRT-008-03⁦9%⁩Dr. Lina S. Al-Hazzani⁦2025-10-29⁩2025-10-297 Jumada I 1447 AHApproved
  • Solution design008-D4 · V1 · CRT-008-04⁦9%⁩Eng. Ziyad A. Al-Dakheel⁦2025-12-18⁩2025-12-1827 Jumada II 1447 AHApproved
  • Release 1008-D5 · V1 · CRT-008-05⁦14%⁩Eng. Ziyad A. Al-Dakheel⁦2026-02-06⁩2026-02-0618 Shaʻban 1447 AHApproved
  • Release 2008-D6 · V1 · CRT-008-06⁦14%⁩Karim Haddad⁦2026-03-27⁩2026-03-278 Shawwal 1447 AHApproved
  • Integrations008-D7 · V1 · CRT-008-07⁦14%⁩Dr. Lina S. Al-Hazzani⁦2026-05-16⁩2026-05-1629 Dhuʻl-Qiʻdah 1447 AHApproved
  • System testing008-D8 · V1 · CRT-008-08⁦11%⁩Karim Haddad⁦2026-07-04⁩2026-07-0419 Muharram 1448 AHApproved
  • User acceptance testing008-D9 · V1 · CRT-008-09⁦11%⁩Dr. Lina S. Al-Hazzani⁦2026-08-23⁩2026-08-2310 Rabiʻ I 1448 AHApproved
  • Training & change008-D10 · V1⁦5%⁩Dr. Lina S. Al-Hazzani17 days overdue2026-10-1130 Rabiʻ II 1448 AHIn review
  • Go-live & handover008-D11 · V0⁦4%⁩Eng. Ziyad A. Al-DakheelIn 33 days2026-11-3020 Jumada II 1448 AHDraft

Team, contracts & documents

Team

4 members

Karim Haddad · Senior Digital Delivery Consultant — PMOEng. Reem K. Al-Dosari · Head of the My Business Portal & Programme Manager, Digital Member JourneyHala F. Al-Angari · Director General, Sectoral Committees
  • Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOProject managerP-041k.haddad@chamber.sa⁦30%⁩
  • Eng. Reem K. Al-DosariEng. Reem K. Al-DosariHead of the My Business Portal & Programme Manager, Digital Member JourneyProgramme oversight, dispute-settlement platformP-004r.aldosari@chamber.sa⁦15%⁩
  • Hala F. Al-AngariHala F. Al-AngariDirector General, Sectoral CommitteesSectoral committees’ voice in settlement proceduresP-048h.alangari@chamber.sa⁦10%⁩

Documents

  • No documents yet

Meetings

  • No meetings scheduled