Dispute Settlement & Commercial Arbitration Platform — Release 2
Add to watchlistOnline filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.
Budget (BAC)
Actual cost
89% of budget
Progress
Estimate at completion
SPI · CPI
Forecast finish
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2025-09-10 | 2025-09-28 | +18 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2025-12-18 | 2026-01-19 | +32 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-05-16 | 2026-07-07 | +52 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-08-23 | 2026-10-26 | +64 days | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Achieved | 1 | Approved |
| Final handoverMS-G5 | Payment | 2026-11-30 | 2026-11-30 | On time | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | On track | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
91%Awaiting acceptance
5%Not handed in
4%Deliverable flow
Display options
| Project plan & baseline008-D1 | 5% | CRT-008-01 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Dr. Lina S. Al-Hazzani | 2025-07-22 | V1 | 3 of 3 |
| Monitoring & reporting008-D2 | 4% | CRT-008-02 | Approved | Dr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.sa | Dr. Lina S. Al-Hazzani | 2025-09-10 | V1 | 3 of 3 |
| Business requirements008-D3 | 9% | CRT-008-03 | Approved | Dr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.sa | Dr. Lina S. Al-Hazzani | 2025-10-29 | V1 | 3 of 3 |
| Solution design008-D4 | 9% | CRT-008-04 | Approved | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Dr. Lina S. Al-Hazzani | 2025-12-18 | V1 | 3 of 3 |
| Release 1008-D5 | 14% | CRT-008-05 | Approved | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Dr. Lina S. Al-Hazzani | 2026-02-06 | V1 | 3 of 3 |
| Release 2008-D6 | 14% | CRT-008-06 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Dr. Lina S. Al-Hazzani | 2026-03-27 | V1 | 3 of 3 |
| Integrations008-D7 | 14% | CRT-008-07 | Approved | Dr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.sa | Dr. Lina S. Al-Hazzani | 2026-05-16 | V1 | 3 of 3 |
| System testing008-D8 | 11% | CRT-008-08 | Approved | Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa | Dr. Lina S. Al-Hazzani | 2026-07-04 | V1 | 3 of 3 |
| User acceptance testing008-D9 | 11% | CRT-008-09 | Approved | Dr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.sa | Dr. Lina S. Al-Hazzani | 2026-08-23 | V1 | 3 of 3 |
| Training & change008-D10 | 5% | — | Under review | Dr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.sa | Dr. Lina S. Al-Hazzani | 2026-10-11 | V1 | 1 of 3 |
| Go-live & handover008-D11 | 4% | — | Draft | Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa | Dr. Lina S. Al-Hazzani | 2026-11-30 | V0 | 0 of 3 |
| Total · 11 | 100% |