Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-008On track4ExecutionScrumIn progress

Dispute Settlement & Commercial Arbitration Platform — Release 2

Add to watchlist

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Budget (BAC)

SAR 920K

Actual cost

SAR 821K

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 902K

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Scope statementRequired at this stage

What the project delivers, what it does not, and when a deliverable counts as accepted.

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

In scope

  • Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

Acceptance criteria

  • Main deliverable — stage 1Meets the approved specification, signed off by the project owner
  • Main deliverable — final stageMeets the approved specification, signed off by the project owner

Scope baselineRequired at this stage

Every approved change creates a new baseline

  1. 1

    SB-1Current⁦2025-06-01⁩

    Baseline approved at the planning gate

    Budget920KFinish⁦2026-11-30⁩

Requirements registerRequired at this stage

⁦6⁩ requirements of five kinds, with the trace status of each

By type

  • Business1
  • Functional2
  • Technical1
  • Regulatory1
  • Security1

Fully traced

⁦100%⁩

6/6 · linked to a deliverable, task and test

Test passed

⁦17%⁩

1/6 · test result is a pass

Accepted

⁦17%⁩

1/6 · signed off by the business owner

⁦6⁩ results
Export CSV
REQ-008-01An end-to-end digital journey, no walk-inBusinessMustIn progressDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saSB-1
REQ-008-02Nafath single sign-onFunctionalMustIn progressKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saSB-1
REQ-008-03A user dashboardFunctionalMustIn progressDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saSB-1
REQ-008-04Integration with internal systemsTechnicalCouldApprovedKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saSB-1
REQ-008-05⁦WCAG 2⁩.⁦1⁩ accessibilityRegulatoryCouldIn progressDr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.saSB-1
REQ-008-06Essential cybersecurity controlsSecurityShouldIn progressKarim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.saSB-1
⁦1⁩–⁦6⁩ of ⁦6⁩

Traceability matrixRequired at this stage

Requirement → deliverable → task → test → acceptance. No requirement has a gap.

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close