PRJ-2026-008On track4ExecutionScrumIn progress

Dispute Settlement & Commercial Arbitration Platform — Release 2

Add to watchlist

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Budget (BAC)

SAR 920K

Actual cost

SAR 821K

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 902K

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started
Fields required by the project’s stage (Execution): 15 fields required now.Field settings

Riyadh Chamber of Commerce & Industry

Project charter

Dispute Settlement & Commercial Arbitration Platform — Release 2

APPROVEDV2Approved ⁦2025-05-02⁩

1Project identity

Required at this stage
Project name
Dispute Settlement & Commercial Arbitration Platform — Release 2
Project code
PRJ-2026-008
Project sponsor
Eng. Ziyad A. Al-DakheelEng. Ziyad A. Al-DakheelDeputy Secretary-General, Business SupportP-047z.aldakheel@chamber.sa
Project manager
Karim HaddadKarim HaddadSenior Digital Delivery Consultant — PMOP-041k.haddad@chamber.sa
Project owner
Dr. Lina S. Al-HazzaniDr. Lina S. Al-HazzaniExecutive Director, Legal Affairs & Board SecretaryP-052l.alhazzani@chamber.sa
Portfolio & programme
Member Services & Business Voice PortfolioDigital Member Journey Programme
Type & methodology
Digital · Scrum
Current phase
4Execution

2Background & rationale

Required at this stage

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

3Objectives

Required at this stage
  1. 1High-quality, value-adding digital core services for members
  2. 2A better member experience and service quality

4Scope

Required at this stage

In scope

  • Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

5High-level requirements

Required at this stage
  1. 1Single sign-on through Nafath
  2. 2Integration with internal systems
  3. 3Accessibility and UX standards

6Deliverables

Required at this stage
1Project management plan⁦2025-05-27⁩
2Main deliverable — stage 1⁦2026-02-22⁩
3Main deliverable — final stage⁦2026-09-11⁩
4Final report⁦2026-11-30⁩

7Key milestones

Required at this stage
  1. Charter approved⁦2025-05-02⁩
  2. Contract signed⁦2025-08-04⁩
  3. 50% of works complete⁦2026-02-22⁩
  4. Provisional acceptance⁦2026-10-15⁩
  5. Closure⁦2026-11-30⁩

8Budget

Required at this stage
  • Main contract⁦71.7%⁩660K
  • Supervision & consulting⁦14.1%⁩130K
  • Internal team⁦9.2%⁩85K
  • Contingency reserve (⁦5%⁩)⁦4.9%⁩45K
The owning sector’s approved budgetTotal920K

9Timeline

Required at this stage
Start
2025-05-046 Dhuʻl-Qiʻdah 1446 AH
Baseline finish
2026-11-3020 Jumada II 1448 AH
Duration
⁦19⁩ months

10Key risks

Required at this stage
  • No risks recorded yet.

11Constraints

Required at this stage
  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

12Assumptions

Required at this stage
  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

13Stakeholders

Required at this stage
  • Project sponsorDecisions and funding
  • Project ownerAccepts deliverables, owns benefits
  • Project Management Office (PMO)Governance and compliance

14Success criteria

Required at this stage
  1. 1Delivered within the approved budget
  2. 2On the approved date ⁦±5%⁩
  3. 3⁦Target benefits within 12 months⁩

15Governance structure

Required at this stage
  • Change CommitteeApproves scope, cost and schedule changesWeekly
  • PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
  • Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly