PRJ-2026-008On track4ExecutionScrumIn progress

Dispute Settlement & Commercial Arbitration Platform — Release 2

Add to watchlist

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Budget (BAC)

SAR 920K

Actual cost

SAR 821K

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 902K

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Project charter

Objective, scope, deliverables, roles and budget

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Initiation

Project charter

Objective, scope, deliverables, roles and budget

Form no.
RC-PMO-F04
Template edition
3.0
Version
V2
Form date
⁦2025-05-02⁩
Hijri
4 Dhuʻl-Qiʻdah 1446 AH
ApprovedPRJ-2026-008Dispute Settlement & Commercial Arbitration Platform — Release 2

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-008
Project
Dispute Settlement & Commercial Arbitration Platform — Release 2
Portfolio
Member Services & Business Voice Portfolio
Sector
Legal Affairs
Sponsor
Eng. Ziyad A. Al-Dakheel
Project manager
Karim Haddad

1Objective

Background

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Project objectives

  1. High-quality, value-adding digital core services for members
  2. A better member experience and service quality

2Scope

In scope

  • Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.
  • Single sign-on through Nafath
  • Integration with internal systems

Out of scope

  • Operation and maintenance after the warranty period
  • Work outside the approved site or system boundary

3Deliverables and milestones

DeliverableDue
Project management plan⁦2025-05-27⁩
Main deliverable — stage 1⁦2026-02-22⁩
Main deliverable — final stage⁦2026-09-11⁩
Final report⁦2026-11-30⁩
MilestoneDate
Charter approved⁦2025-05-02⁩
Contract signed⁦2025-08-04⁩
50% of works complete⁦2026-02-22⁩
Provisional acceptance⁦2026-10-15⁩
Closure⁦2026-11-30⁩

4RolesAuto-filled

SponsorAuto-filled
Eng. Ziyad A. Al-Dakheel
Project ownerAuto-filled
Dr. Lina S. Al-Hazzani
Project managerAuto-filled
Karim Haddad
StakeholderRole
Project sponsorDecisions and funding
Project ownerAccepts deliverables, owns benefits
Project Management Office (PMO)Governance and compliance
Governance bodyRoleCadence
Change CommitteeApproves scope, cost and schedule changesWeekly
PMO CommitteeMethodology compliance, data quality, stage gatesFortnightly
Project management teamDay-to-day control, risks, impediments, the periodic update cardWeekly

5BudgetAuto-filled

LineAmount
Main contractSAR 660K
Supervision & consultingSAR 130K
Internal teamSAR 85K
Contingency reserve (5%)SAR 45K
Approved budgetSAR 920K

Funding

The owning sector’s approved budget

6Success criteria and constraints

Success criteria

  • Delivered within the approved budget
  • On the approved date ±5%
  • Target benefits within 12 months

Constraints

  • Stay within the approved budget
  • Comply with the Government Tenders & Procurement Law

Assumptions

  • Named internal staff available throughout
  • Approvals land within the workflow’s action time limits

Approval logChain: Project charter approval · version ⁦1⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Karim HaddadSenior Digital Delivery Consultant — PMOSubmitted—⁦2025-04-23⁩ 10:00
2PMO complianceMethodology reviewDr. Noura M. Al-OtaibiPMO — directorApproved—⁦2025-04-26⁩ 12:30
3Project ownerTechnical acceptanceDr. Lina S. Al-HazzaniProject ownerApproved—⁦2025-04-29⁩ 09:45
4Budget funding confirmedFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2025-04-30⁩ 11:10
5Sponsor approvalTechnical acceptanceEng. Ziyad A. Al-DakheelProject sponsorApproved—⁦2025-05-02⁩ 11:00

Signatures

PMO compliance

Dr. Noura M. Al-Otaibi

Approved⁦2025-04-26⁩

Project owner

Dr. Lina S. Al-Hazzani

Approved⁦2025-04-29⁩

Budget funding confirmed

Munirah A. Al-Khalidi

Approved⁦2025-04-30⁩

Sponsor approval

Eng. Ziyad A. Al-Dakheel

Approved⁦2025-05-02⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F04 · version V2

Project charter

Prints the form and its approval log on A4.

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Project charter approval · version ⁦1⁩

Submitted by Karim Haddad on ⁦2025-04-23⁩

  1. Methodology review

    PMO compliance

    Dr. Noura M. Al-Otaibi · PMO — director

    Approved · ⁦2025-04-26⁩ at ⁦12:30⁩

  2. Technical acceptance

    Project owner

    Dr. Lina S. Al-Hazzani · Project owner

    Approved · ⁦2025-04-29⁩ at ⁦09:45⁩

  3. Financial approval

    Budget funding confirmed

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2025-04-30⁩ at ⁦11:10⁩

  4. Technical acceptance

    Sponsor approval

    Eng. Ziyad A. Al-Dakheel · Project sponsor

    Approved · ⁦2025-05-02⁩ at ⁦11:00⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2025-05-02⁩

    Approved version

    • PMO comments addressed

    Karim Haddad

  2. V1Returned for edit⁦2025-04-13⁩

    First draft

    • Returned to detail the budget

    Karim Haddad