PRJ-2026-008On track4ExecutionScrumIn progress

Dispute Settlement & Commercial Arbitration Platform — Release 2

Add to watchlist

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Budget (BAC)

SAR 920K

Actual cost

SAR 821K

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 902K

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Finance & earned value

The full budget structure, cost broken down by eight dimensions, cash flow with its S-curve, and earned-value indicators with an automatic end-of-project forecast.

Budget anatomy

The approved SAR 920K split into spent, committed and left, with the estimate at completion

EAC SAR 902K
Revised request SAR 920K
  • Actual spendSAR 821K
  • Committed, not spentSAR 24K
  • Allotted, uncommittedSAR 47.4K
  • Contingency availableSAR 27.6K

Budget

EstimatedManualFrom the project proposal — not from the finance systemthe proposal’s cost before approval
SAR 855K
Original budgetwhen the first baseline was approved
SAR 920K
Approved budgetafter approved change requests
SAR 920K
Current budgetavailable to spend now
SAR 920K
Revised budgetif the pending changes are approved
SAR 920K

Commitments

CommitmentsSyncedFrom the nightly finance-system syncsigned contracts and purchase orders
SAR 845K
Contracts1 active contract
SAR 740K
Purchase orders⁦2⁩ orders
SAR 105K
Remaining budgetapproved less actual
SAR 99K

Spend & outlook

Actual costSyncedFrom the nightly finance-system syncincluding accruals
SAR 821K
Accrualswork done, not yet invoiced
SAR 33K
Estimate at completionManualThe project manager’s estimate — not from the finance systemthe PM’s bottom-up forecast
SAR 902K
ContingencySAR 18.4K drawn of SAR 46K
SAR 27.6K

Estimated vs approved budget

What the project proposal estimated before approval, against today’s approved budget and the estimate at completion

EstimatedSAR 855K
ApprovedSAR 920K
Estimate at completionSAR 902K
Approved is SAR 65K (⁦7.6%⁩) above the estimate
The estimate at completion is SAR 47K (⁦5.5%⁩) above the estimate

From the «project proposal & feasibility study» approved at the approval gate on ⁦2025-02-18⁩ · The gap between estimated and approved comes from the scope update and the change requests approved after the approval gate.

ERP link — data readiness

The link keys are ready for the finance-system sync; Munjaz follows the project and does not replace the accounting system

⁦4⁩ of ⁦4⁩ fields ready
  • Cost centreCC-90008
  • WBS elements⁦5⁩ elements · P-2026-008.01 …
  • Purchase orders⁦2⁩ synced · ⁦0⁩ manual
  • Invoices & certificates⁦11⁩ posted · ⁦0⁩ in approval
Last sync⁦2026-10-28⁩ · 06:00 · succeededNext tonight at 02:00

Where each figure comes from

  • EstimatedManualFrom the project proposal — not from the finance system
  • CommitmentsSyncedFrom the nightly finance-system sync
  • Actual costSyncedFrom the nightly finance-system sync
  • Estimate at completionManualThe project manager’s estimate — not from the finance system

Once the link is live, synced figures are read from the finance system; manual updates stay available to the same roles and are logged.

Purchase-order register

Manual edit log

Every manual update — who, when, why and from which source

No manual edits on this project

All its figures come from the finance-system sync. Finance & procurement — and the project manager, for the estimate at completion — can update them by hand.

Budget bridge

From the original to the revised request

  • Total
  • Increase
  • Decrease

Contingency draw-downs

SAR 18.4K drawn of SAR 46K

  • Covering realised delivery risks⁦2026-08-29⁩SAR 18.4K

Purchase orders

Cost breakdown structure

Every dimension adds up to the same totals

Cost breakdown structure — WBS
ItemBudgetSAR MCommittedSAR MActualSAR MEACSAR MVarianceSAR MConsumption
1Management & governance0.070.070.070.07⁦−0.00⁩
2Analysis & design0.150.150.150.15⁦−0.00⁩
3Build0.360.360.360.36⁦−0.00⁩
4Testing & acceptance0.180.180.180.18⁦−0.00⁩
5Launch & handover0.130.080.050.12⁦+0.01⁩
Unallocated contingency0.030.000.000.01⁦+0.01⁩
Total0.920.850.820.90⁦+0.02⁩

Budget split

WBS

SAR 920K

Budget

  • Management & governanceSAR 71.4K⁦8%⁩
  • Analysis & designSAR 151.7K⁦16%⁩
  • BuildSAR 357K⁦39%⁩
  • Testing & acceptanceSAR 178.5K⁦19%⁩
  • Launch & handoverSAR 133.9K⁦15%⁩
  • Unallocated contingencySAR 27.6K⁦3%⁩

Cash flow

Planned, committed, actual and forecast

Spend per period

SAR millions

  • Planned
  • Actual
  • Forecast

Cumulative S-curve

Cumulative to close

  • Actual, then forecast
  • Planned, cumulative
  • Committed, cumulative

Earned value management

At the data date ⁦2026-10-28⁩

Planned value, earned value and actual cost

  • Planned value
  • Earned value
  • Actual cost
  • Estimate at completion
  • Budget at completion

Finish by earned schedule

⁦2027-03-02⁩+92

SPI(t) ⁦0.86⁩ against the approved finish ⁦2026-11-30⁩

Planned valuePV
SAR 913K
The value of the work that should be done by today.
PV
Earned valueEV
SAR 837K
The value of the work actually done, at plan prices.
EV = % complete × BAC
Actual costAC
SAR 821K
What has actually been spent on the work done.
AC
Budget at completionBAC
SAR 920K
The approved budget for the whole project.
BAC
Cost varianceCV
⁦+0.02⁩ SAR M
Earned less actual; negative means paying more than the value.
CV = EV − AC
Schedule varianceSV
⁦−0.08⁩ SAR M
Earned less planned; negative means behind, in value.
SV = EV − PV
Cost performance indexCPI
1.02
Value produced per riyal spent; under 1 is an overrun.
CPI = EV ÷ AC
Schedule performance indexSPI
0.92
Work done over work planned; under 1 is behind.
SPI = EV ÷ PV
Estimate at completionEAC
SAR 902K
What the project will cost when it finishes, as forecast.
EAC = BAC ÷ CPI
Estimate to completeETC
SAR 81K
What is still to be spent to completion.
ETC = EAC − AC
Variance at completionVAC
⁦+0.02⁩ SAR M
Budget less the estimate; negative is an overrun.
VAC = BAC − EAC
To-complete performance indexTCPI
0.84
The cost efficiency the rest must reach to stay on budget.
TCPI = (BAC − EV) ÷ (BAC − AC)

Automatic end-of-project forecast

Four ways to estimate the final cost, and the date earned schedule points to

  • At today’s cost performanceSAR 902.4K
  • If the rest goes to planSAR 904K
  • At cost and schedule performanceSAR 909.8K
  • The PM’s bottom-up estimateSAR 902K
  • The performance needed on the rest is below what has been achieved; the budget holds.

Estimate at completion at that performance

SAR 902.4K

Variance at completion: ⁦+0.02⁩ SAR M