Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-008On track4ExecutionScrumIn progress

Dispute Settlement & Commercial Arbitration Platform — Release 2

Add to watchlist

Online filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.

Budget (BAC)

SAR 920K

Actual cost

SAR 821K

⁦89%⁩ of budget

Progress

⁦91%⁩Awaiting acceptance ⁦5%⁩

Estimate at completion

SAR 902K

SPI · CPI

1.01Schedule performance index · 1.011.02Cost performance index · 1.02

Forecast finish

⁦2026-11-26⁩

On baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure15 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started

Work breakdown structure

The project’s scope broken down from phase to subtask, with codes, owners, durations, dates, progress, cost, links and deliverables. Drag any element to re-order it among its siblings; the codes renumber.

Structure levels

Pick a level to open the tree to that depth

Allotted to work892.4K⁦16⁩ elements
Unallocated contingency27.6KSAR 46K
Budget at completion920KPRJ-2026-008
Weighted progress⁦91%⁩Linked deliverables: 0
ElementLevelOwnerDurationStart – finishProgressBudgetSAR MActualSAR MLinksDeliverables
Project575⁦2025-05-04⁩⁦2026-11-30⁩⁦91%⁩0.890.82—
1
Phase147⁦2025-05-04⁩⁦2025-09-28⁩⁦100%⁩0.070.07—
1.1
WBS element90⁦2025-05-04⁩⁦2025-08-02⁩⁦100%⁩0.040.040 / 1
1.2
WBS element91⁦2025-06-29⁩⁦2025-09-28⁩⁦100%⁩0.040.041 / 2
2
Phase147⁦2025-08-25⁩⁦2026-01-19⁩⁦100%⁩0.150.15—
2.1
WBS element90⁦2025-08-25⁩⁦2025-11-23⁩⁦100%⁩0.080.081 / 1
2.2
WBS element91⁦2025-10-20⁩⁦2026-01-19⁩⁦100%⁩0.080.081 / 2
3
Phase203⁦2025-12-16⁩⁦2026-07-07⁩⁦100%⁩0.360.36—
3.1
WBS element90⁦2025-12-16⁩⁦2026-03-16⁩⁦100%⁩0.120.121 / 1
3.2
WBS element91⁦2026-02-10⁩⁦2026-05-12⁩⁦100%⁩0.120.121 / 1
3.3
WBS element90⁦2026-04-08⁩⁦2026-07-07⁩⁦100%⁩0.120.121 / 2
4
Phase145⁦2026-06-03⁩⁦2026-10-26⁩⁦100%⁩0.180.18—
4.1
WBS element90⁦2026-06-03⁩⁦2026-09-01⁩⁦100%⁩0.090.091 / 1
4.2
WBS element88⁦2026-07-30⁩⁦2026-10-26⁩⁦100%⁩0.090.091 / 2
5
Phase129⁦2026-07-24⁩⁦2026-11-30⁩⁦40%⁩0.130.05—
5.1
WBS element112⁦2026-07-24⁩⁦2026-11-13⁩⁦80%⁩0.070.051 / 1
5.2
WBS element21⁦2026-11-05⁩⁦2026-11-26⁩⁦0%⁩0.07—1 / 1
Total⁦91%⁩0.890.82
Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close