PRJ-2026-008On track4ExecutionScrumIn progress
Dispute Settlement & Commercial Arbitration Platform — Release 2
Add to watchlistOnline filing of amicable-settlement and arbitration requests between businesses, the roster of accredited arbitrators and conciliators, and remote settlement sessions and their records.
Project managerKarim HaddadProject sponsorEng. Ziyad A. Al-DakheelProgrammeDigital Member Journey Programme
Budget (BAC)
SAR 920K
Actual cost
SAR 821K
89% of budget
Progress
91%Awaiting acceptance 5%
Estimate at completion
SAR 902K
SPI · CPI
1.01Schedule performance index · 1.011.02Cost performance index · 1.02
Forecast finish
2026-11-26
On baseline
ExecutionStage 4 of 5
Next gate:Closure15 October 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate5 March 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate4 May 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate4 August 2025Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate15 October 2026Closure · Not startedClosure · Not started