Chamber Cybersecurity Programme Subtask Last item under this branch 2027-01-02 88% Chamber Cybersecurity Programme Planned: 2025-02-02 → 2026-12-15 Forecast: 2025-02-02 → 2027-01-02 Float: 0d
1 Management & governance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-07-23 100% Management & governance Planned: 2025-02-02 → 2025-07-05 Actual: 2025-02-02 → 2025-07-23
1.1 Project plan & baseline Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-05-18 100% Project plan & baseline Planned: 2025-02-02 → 2025-05-07 Actual: 2025-02-02 → 2025-05-18
1.2 Monitoring & reporting Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-23 100% Monitoring & reporting Planned: 2025-04-02 → 2025-07-05 Actual: 2025-04-09 → 2025-07-23
Project plan approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-07-23 100% Project plan approved Planned: 2025-07-05 → 2025-07-05 Actual: 2025-07-23 → 2025-07-23 Project plan approved
2 Analysis & design Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2025-12-02 100% Analysis & design Planned: 2025-05-30 → 2025-10-30 Actual: 2025-06-14 → 2025-12-02
2.1 Business requirements Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-09-27 100% Business requirements Planned: 2025-05-30 → 2025-09-01 Actual: 2025-06-14 → 2025-09-27
2.2 Solution design Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-02 100% Solution design Planned: 2025-07-28 → 2025-10-30 Actual: 2025-08-19 → 2025-12-02
Designs approved Task after this Starts when this one finishes Milestone after this Falls on its finish 2025-12-02 100% Designs approved Planned: 2025-10-30 → 2025-10-30 Actual: 2025-12-02 → 2025-12-02 Designs approved
3 Build Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-06-18 100% Build Planned: 2025-09-25 → 2026-04-24 Actual: 2025-10-24 → 2026-06-18
3.1 Release 1 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-02-06 100% Release 1 Planned: 2025-09-25 → 2025-12-28 Actual: 2025-10-24 → 2026-02-06
3.2 Release 2 Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-04-13 100% Release 2 Planned: 2025-11-23 → 2026-02-24 Actual: 2025-12-28 → 2026-04-13
3.3 Integrations Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-18 100% Integrations Planned: 2026-01-20 → 2026-04-24 Actual: 2026-03-04 → 2026-06-18
Build complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-06-18 100% Build complete Planned: 2026-04-24 → 2026-04-24 Actual: 2026-06-18 → 2026-06-18 Build complete
4 Testing & acceptance Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2026-10-26 100% Testing & acceptance Planned: 2026-03-20 → 2026-08-20 Actual: 2026-05-09 → 2026-10-26
4.1 System testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-08-23 100% System testing Planned: 2026-03-20 → 2026-06-22 Actual: 2026-05-09 → 2026-08-23
4.2 User acceptance testing Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% User acceptance testing Planned: 2026-05-18 → 2026-08-20 Actual: 2026-07-14 → 2026-10-26
Testing & acceptance complete Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-10-26 100% Testing & acceptance complete Planned: 2026-08-20 → 2026-08-20 Actual: 2026-10-26 → 2026-10-26 Testing & acceptance complete
5 Launch & handover Subtask Last item under this branch Task after this Starts when the last work in it finishes Milestone after this Falls on its finish 2027-01-02 20% Launch & handover Planned: 2026-07-15 → 2026-12-15 Forecast: 2026-07-15 → 2027-01-02 Float: 0d
5.1 Training & change Task after this Starts when this one finishes Milestone after this Falls on its finish 2026-12-23 40% Training & change Planned: 2026-07-15 → 2026-10-17 Forecast: 2026-07-15 → 2026-12-23 Float: 0d Drag to change its duration +67
5.2 Go-live & handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-02 0% Go-live & handover Planned: 2026-09-12 → 2026-12-15 Forecast: 2026-12-17 → 2027-01-02 Float: 0d Drag to change its dates +18
Final handover Task after this Starts when this one finishes Milestone after this Falls on its finish 2027-01-02 0% Final handover Planned: 2026-12-15 → 2026-12-15 Forecast: 2027-01-02 → 2027-01-02 Float: 0d Drag to change its dates Final handover