PRJ-2026-007Critical4ExecutionConstructionStalled

Training & Employment Centre Complex

Remove from watchlist

A 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.

Early warning: ⁦97%⁩ chance of slipping within ⁦30⁩ days

Budget (BAC)

SAR 32M

Actual cost

SAR 22.2M

⁦70%⁩ of budget

Progress

⁦57%⁩Awaiting acceptance ⁦10%⁩

Estimate at completion

SAR 39M

SAR +7M

SPI · CPI

0.70Schedule performance index · 0.700.82Cost performance index · 0.82

Forecast finish

⁦2027-06-01⁩

152 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure7 October 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate6 December 2023Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate4 February 2024Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionGoDate23 July 2024Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate7 October 2026Closure · Not startedClosure · Not started

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Proposal

Project proposal & feasibility study

Justification, objectives, benefits, cost and initial risks

Form no.
RC-PMO-F01
Template edition
2.1
Version
V2
Form date
⁦2023-07-09⁩
Hijri
21 Dhuʻl-Hijjah 1444 AH
ApprovedDMD-2026-007Training & Employment Centre Complex

Auto-filled — Filled by the platform from the project record, not typed.

Project code
PRJ-2026-007
Project
Training & Employment Centre Complex
Portfolio
Branches, Service & Training Centres Portfolio
Sector
Training & Employment Centre
Sponsor
Eng. Turki A. Al-Anazi
Project manager
Eng. Shahad M. Al-Malki

1The proposalAuto-filled

TitleAuto-filled
Training & Employment Centre Complex
Proposed byAuto-filled
Eng. Shahad M. Al-Malki
DepartmentAuto-filled
Training Programmes Department
Submitted onAuto-filled
⁦2023-07-09⁩
Proposal numberAuto-filled
DMD-2026-007

2Justification

A 92,000 m² complex with 42 training rooms, practical labs and a job-fair hall, ending the lease of 9 training venues.

3Objectives

  1. Empower entrepreneurship, SMEs and employment
  2. Financial sustainability

Strategic objectives served

  • SO-2.4 — Empower entrepreneurship, SMEs and employment
  • SO-4.1 — Financial sustainability

4Expected benefits

KindBenefit
No benefits recorded yet

5Cost & feasibility

Estimated cost

SAR 32M

Funding

The owning sector’s approved budget

Cost lineAmount
Main contractSAR 23M
Supervision & consultingSAR 4.5M
Internal teamSAR 2.9M
Contingency reserve (5%)SAR 1.6M
TotalSAR 32M

6Initial risks

RiskLevelProposed response
Contractor financial claims piling up over unapproved variationsHighTreated in the risk management plan
Late delivery of curtain-wall glazing from the overseas factoryHighTreated in the risk management plan
Possible removal of the MEP subcontractorHighTreated in the risk management plan

Approval logChain: Proposal & feasibility approval · version ⁦4⁩

Every decision on the form — who, their role, the note and the time. It prints with the form.

#StepKindNameDecisionNoteDate & time
1Author—Eng. Shahad M. Al-MalkiSenior Project Manager — Buildings & FacilitiesSubmitted—⁦2023-07-09⁩ 09:06
2Line manager endorsementTechnical acceptanceEng. Reem K. Al-DosariThe requester’s line managerApproved—⁦2023-07-10⁩ 13:46
3PMO reviewMethodology reviewGhada A. Al-ShahraniPMO — analystApproved—⁦2023-07-13⁩ 14:53
4Portfolio manager reviewTechnical acceptanceEng. Abdulrahman S. Al-HarbiPortfolio managerApprovedConsistent with the portfolio plan and its priorities.⁦2023-07-16⁩ 09:00
5Cost & funding reviewFinancial approvalMunirah A. Al-KhalidiFinanceApproved—⁦2023-07-19⁩ 09:42
6Project Approval CommitteeTechnical acceptanceDr. Noura M. Al-OtaibiProject Approval CommitteeApproved—⁦2023-07-24⁩ 11:14

Signatures

Line manager endorsement

Eng. Reem K. Al-Dosari

Approved⁦2023-07-10⁩

PMO review

Ghada A. Al-Shahrani

Approved⁦2023-07-13⁩

Portfolio manager review

Eng. Abdulrahman S. Al-Harbi

Approved⁦2023-07-16⁩

Cost & funding review

Munirah A. Al-Khalidi

Approved⁦2023-07-19⁩

Project Approval Committee

Dr. Noura M. Al-Otaibi

Approved⁦2023-07-24⁩

Issued from Munjaz — Riyadh Chamber · ⁦2026-10-28⁩Form RC-PMO-F01 · version V2

Project proposal & feasibility study

Prints the form and its approval log on A4.

Project charter

Approval path

Read from the approval engine: the steps, their holders and the time limits in working days.

Chain: Proposal & feasibility approval · version ⁦4⁩

Submitted by Eng. Shahad M. Al-Malki on ⁦2023-07-09⁩

  1. Technical acceptance

    Line manager endorsement

    Eng. Reem K. Al-Dosari · The requester’s line manager

    Approved · ⁦2023-07-10⁩ at ⁦13:46⁩

  2. Methodology review

    PMO review

    Ghada A. Al-Shahrani · PMO — analyst

    Approved · ⁦2023-07-13⁩ at ⁦14:53⁩

  3. Technical acceptance

    Portfolio manager review

    Eng. Abdulrahman S. Al-Harbi · Portfolio manager

    Approved · ⁦2023-07-16⁩ at ⁦09:00⁩

    Consistent with the portfolio plan and its priorities.

  4. Financial approval

    Cost & funding review

    Munirah A. Al-Khalidi · Finance

    On the path because: Financial link?

    Approved · ⁦2023-07-19⁩ at ⁦09:42⁩

  5. Technical acceptance

    Project Approval Committee

    Dr. Noura M. Al-Otaibi · Project Approval Committee

    Approved · ⁦2023-07-24⁩ at ⁦11:14⁩

Approval complete — the form is approved and in force.

Previous versions

Every version is kept with its status and what changed.

  1. V2ApprovedCurrent⁦2023-07-30⁩

    Approved after the PMO’s comments

    • Cost estimate updated after indicative quotes
    • Initial risks and their responses added

    Eng. Shahad M. Al-Malki

  2. V1Returned for edit⁦2023-07-09⁩

    First draft — returned to complete the cost and risks

    • First version of the proposal

    Eng. Shahad M. Al-Malki