Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-019At risk4ExecutionConstructionIn progress

New Premium Members Centre & VIP Lounges

Add to watchlist

A full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.

Budget (BAC)

SAR 7.9M

Actual cost

SAR 4.2M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 8.1M

SAR +161K

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

New Premium Members Centre & VIP Lounges

PRJ-2026-019 · Member Experience & Business Development Sector · Strategic · WP-2025-019

In progressAt risk4ExecutionProject manager: Eng. Fahad T. Al-Sulami · Sponsor: Eng. Sami A. Al-Fraih
Progress
⁦52%⁩ / ⁦56%⁩
SPI · CPI
0.93 · 0.98
Spend
SAR 4.2M / SAR 7.9M
Estimate at completion
SAR 8.1M

Schedule

⁦4%⁩ behind⁦52%⁩

Planned to date ⁦56%⁩

Forecast finish: 2027-03-124 Shawwal 1448 AH · 12 days late

SPI0.93Schedule performance index · 0.93CPI0.98Cost performance index · 0.98

Health dimensions

At risk

Last update: 2026-10-2514 Jumada I 1448 AH · Up to date

Deliverables

⁦6⁩ of ⁦9⁩ due deliverables accepted on time (⁦67%⁩)

Next milestones

  • Build complete2026-11-2616 Jumada II 1448 AH
  • Testing & acceptance complete2027-01-2820 Shaʻban 1448 AH
  • Final handover2027-03-113 Shawwal 1448 AH

Top risks

  • Late supply of audio-visual systems for the Premium Members Centre rooms9

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 7.9M: 0 on track and 0 red or critical. Weighted progress is 52% against 56% planned, spend SAR 4.2M, and EAC SAR 8.1M (SAR 0.2M over).

No project is more than a month behind baseline.

Riyadh Chamber of Commerce & Industry · prepared by Eng. Fahad T. Al-Sulami in MunjazInternal

Status: At risk ·Project page