PRJ-2026-019At risk4ExecutionConstructionIn progress

New Premium Members Centre & VIP Lounges

Add to watchlist

A full service centre for premium members with lounges, meeting rooms and audio-visual systems, handling premium-class transactions and special services.

Budget (BAC)

SAR 7.9M

Actual cost

SAR 4.2M

⁦53%⁩ of budget

Progress

⁦52%⁩Awaiting acceptance ⁦11%⁩

Estimate at completion

SAR 8.1M

SAR +161K

SPI · CPI

0.93Schedule performance index · 0.930.98Cost performance index · 0.98

Forecast finish

⁦2027-03-12⁩

12 days behind baseline

ExecutionStage ⁦4⁩ of ⁦5⁩

Next gate:Closure2 January 2027

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionGoDate15 January 2025Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 March 2025Planning · CompletePlanning · Complete
  4. Gate into «Execution»DecisionConditional goDate8 July 2025Execution · Current stageExecution · Current stage
  5. Gate into «Closure»DecisionNot held yetDate2 January 2027Closure · Not startedClosure · Not started

Milestones

Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.

Milestone runway

2Achieved
1On track
1At risk
1Late
Average delay104 days
Oct 25Jan 26Apr 26Jul 26Oct 26Jan 27Apr 27
Contractual
Build completePlanned: ⁦2026-05-21⁩Forecast / actual: ⁦2026-11-26⁩Delay: 189 daysG3 +189
Executive
Project plan approvedPlanned: ⁦2025-08-10⁩Forecast / actual: ⁦2025-11-04⁩Delay: 86 daysG1 +86
Payment
Final handoverPlanned: ⁦2027-02-28⁩Forecast / actual: ⁦2027-03-11⁩Delay: 11 daysG5 +11
Regulatory
Testing & acceptance completePlanned: ⁦2026-11-07⁩Forecast / actual: ⁦2027-01-28⁩Delay: 82 daysG4 +82
Project
Designs approvedPlanned: ⁦2025-12-02⁩Forecast / actual: ⁦2026-05-02⁩Delay: 151 daysG2 +151

The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay

Milestone register

⁦5⁩ results
Export CSV
Project plan approvedMS-G1Executive⁦2025-08-10⁩⁦2025-11-04⁩⁦+86⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saAchieved1Approved
Designs approvedMS-G2Project⁦2025-12-02⁩⁦2026-05-02⁩⁦+151⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saAchieved1Approved
Build completeMS-G3Contractual⁦2026-05-21⁩⁦2026-11-26⁩⁦+189⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saLate0Not requested
Testing & acceptance completeMS-G4Regulatory⁦2026-11-07⁩⁦2027-01-28⁩⁦+82⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saAt risk0Not requested
Final handoverMS-G5Payment⁦2027-02-28⁩⁦2027-03-11⁩⁦+11⁩ daysEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saOn track0Not requested
⁦1⁩–⁦5⁩ of ⁦5⁩

Deliverables register

Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.

Progress counted from deliverables

Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.

Weights sum to ⁦100%⁩

Counted

⁦52%⁩

Awaiting acceptance

⁦11%⁩

Not handed in

⁦37%⁩

Deliverable flow

Pick a stage to filter the register
⁦12⁩ results
Export CSV
Project plan & baseline019-D1⁦4%⁩CRT-019-01ApprovedEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saBadr N. Al-Haqbani⁦2025-06-15⁩V1⁦3⁩ of ⁦3⁩
Monitoring & reporting019-D2⁦4%⁩CRT-019-02ApprovedBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2025-08-10⁩V1⁦3⁩ of ⁦3⁩
Detailed design019-D3⁦7%⁩CRT-019-03ApprovedBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2025-10-06⁩V1⁦3⁩ of ⁦3⁩
Permits & approvals019-D4⁦7%⁩CRT-019-04ApprovedEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.saBadr N. Al-Haqbani⁦2025-12-02⁩V1⁦3⁩ of ⁦3⁩
Site works & excavation019-D5⁦15%⁩CRT-019-05ApprovedEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.saBadr N. Al-Haqbani⁦2026-01-27⁩V1⁦3⁩ of ⁦3⁩
Structure019-D6⁦15%⁩CRT-019-06ApprovedEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saBadr N. Al-Haqbani⁦2026-03-25⁩V1⁦3⁩ of ⁦3⁩
Finishes019-D7⁦11%⁩—Under reviewBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2026-05-21⁩V1⁦1⁩ of ⁦3⁩
Supply019-D8⁦9%⁩—DraftEng. Fahad T. Al-SulamiEng. Fahad T. Al-SulamiSenior Project Manager — Branches & Service CentresP-023f.alsulami@chamber.saBadr N. Al-Haqbani⁦2026-07-16⁩V0⁦0⁩ of ⁦3⁩
Installation019-D9⁦8%⁩—DraftBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2026-09-11⁩V0⁦0⁩ of ⁦3⁩
Testing & commissioning019-D10⁦8%⁩—DraftEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.saBadr N. Al-Haqbani⁦2026-11-07⁩V0⁦0⁩ of ⁦3⁩
Provisional acceptance019-D11⁦6%⁩—DraftBadr N. Al-HaqbaniBadr N. Al-HaqbaniDirector General, Membership & AttestationP-046b.alhaqbani@chamber.saBadr N. Al-Haqbani⁦2027-01-02⁩V0⁦0⁩ of ⁦3⁩
Final acceptance019-D12⁦6%⁩—DraftEng. Sami A. Al-FraihEng. Sami A. Al-FraihAssistant Secretary-General, Member Experience & Business DevelopmentP-049s.alfraih@chamber.saBadr N. Al-Haqbani⁦2027-02-28⁩V0⁦0⁩ of ⁦3⁩
Total · 12⁦100%⁩
⁦1⁩–⁦12⁩ of ⁦12⁩