Project status card
28 October 2026 · 17 Jumada I 1448 AH
Entrepreneurship Fast Track Platform
PRJ-2026-027 · Training & Employment Centre · Strategic · WP-2025-027
- Progress
- 63% / 72%
- SPI · CPI
- 0.88 · 0.98
- Spend
- SAR 206K / SAR 320K
- Estimate at completion
- SAR 327K
Schedule
Planned to date 72%
Forecast finish: 2027-01-3123 Shaʻban 1448 AH · 31 days late
SPI0.88Schedule performance index · 0.88CPI0.98Cost performance index · 0.98Health dimensions
Last update: 2026-09-2413 Rabiʻ II 1448 AH · Update overdue
Deliverables
5 of 9 due deliverables accepted on time (56%)
Next milestones
- Build complete2026-11-111 Jumada II 1448 AH
- Testing & acceptance complete2026-12-2112 Rajab 1448 AH
- Final handover2027-01-3022 Shaʻban 1448 AH
Top risks
- Low uptake of the Fast Track readiness assessment among start-ups9
Open impediments
- None
Decisions and changes waiting
- None
Copilot summary
The scope holds 1 project with a budget of SAR 0.3M: 0 on track and 0 red or critical. Weighted progress is 63% against 72% planned, spend SAR 0.2M, and EAC SAR 0.3M (SAR 0M over).
1 project is more than a month behind baseline; the worst: Entrepreneurship Fast Track Platform (31 days).