Entrepreneurship Fast Track Platform
Add to watchlistReadiness assessment and growth plans for start-ups, matched with mentoring, workspaces and funders.
Budget (BAC)
Actual cost
64% of budget
Progress
Estimate at completion
SAR +7,000
SPI · CPI
Forecast finish
31 days behind baseline
ExecutionStage 4 of 5
Next gate:Closure27 November 2026
- Pre-start · CompletePre-start · Complete
- Gate into «Initiation»DecisionGoDate3 September 2025Initiation · CompleteInitiation · Complete
- Gate into «Planning»DecisionGoDate2 November 2025Planning · CompletePlanning · Complete
- Gate into «Execution»DecisionGoDate9 January 2026Execution · Current stageExecution · Current stage
- Gate into «Closure»DecisionNot held yetDate27 November 2026Closure · Not startedClosure · Not started
Milestones
Contractual, executive, payment, regulatory and project milestones: planned, forecast and actual dates, delay, owner, evidence and approval.
Milestone runway
The hollow diamond is the approved baseline date, the solid one the actual or forecast, the line between them the delay
Milestone register
Display options
| Project plan approvedMS-G1 | Executive | 2026-02-05 | 2026-03-24 | +47 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Achieved | 1 | Approved |
| Designs approvedMS-G2 | Project | 2026-04-19 | 2026-07-11 | +83 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Achieved | 1 | Approved |
| Build completeMS-G3 | Contractual | 2026-08-07 | 2026-11-11 | +96 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Late | 0 | Not requested |
| Testing & acceptance completeMS-G4 | Regulatory | 2026-10-19 | 2026-12-21 | +63 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Late | 0 | Not requested |
| Final handoverMS-G5 | Payment | 2026-12-31 | 2027-01-30 | +30 days | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | At risk | 0 | Not requested |
Deliverables register
Each deliverable with its acceptance criteria, files, versions, reviewer and approver, through its states from draft to approved.
Progress counted from deliverables
Project progress = the sum of the weights of deliverables accepted with a completion certificate. Nothing counts before it is accepted and certified.
Weights sum to 100%
Counted
63%Awaiting acceptance
10%Not handed in
27%Deliverable flow
Display options
| Project plan & baseline027-D1 | 5% | CRT-027-01 | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2025-12-30 | V1 | 3 of 3 |
| Monitoring & reporting027-D2 | 5% | CRT-027-02 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-02-05 | V1 | 3 of 3 |
| Business requirements027-D3 | 11% | CRT-027-03 | Approved | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-03-14 | V1 | 3 of 3 |
| Solution design027-D4 | 10% | CRT-027-04 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-04-19 | V1 | 3 of 3 |
| Release 1027-D5 | 16% | CRT-027-05 | Approved | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-05-26 | V1 | 3 of 3 |
| Release 2027-D6 | 16% | CRT-027-06 | Approved | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-07-01 | V1 | 3 of 3 |
| Integrations027-D7 | 10% | — | Under review | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-08-07 | V1 | 1 of 3 |
| System testing027-D8 | 8% | — | Draft | Ghada A. Al-ShahraniGhada A. Al-ShahraniDirector, Entrepreneurship & Young BusinesspeopleP-029g.alshahrani@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-09-12 | V0 | 0 of 3 |
| User acceptance testing027-D9 | 7% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-10-19 | V0 | 0 of 3 |
| Training & change027-D10 | 6% | — | Draft | Eng. Abdulrahman S. Al-HarbiEng. Abdulrahman S. Al-HarbiDirector General, Training & EntrepreneurshipP-014ab.alharbi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-11-24 | V0 | 0 of 3 |
| Go-live & handover027-D11 | 6% | — | Draft | Eng. Turki A. Al-AnaziEng. Turki A. Al-AnaziExecutive Director, Training & Employment CentreP-010t.alanazi@chamber.sa | Eng. Abdulrahman S. Al-Harbi | 2026-12-31 | V0 | 0 of 3 |
| Total · 11 | 100% |