Riyadh ChamberMunjaz11My actionsNotifications
PRJ-2026-029On track3PlanningWaterfallNot started

Training Centre e-Learning Platform

Add to watchlist

A learning platform for the internationally accredited programmes and remote training for member businesses’ staff and the chamber’s employees.

Budget (BAC)

SAR 375K

Actual cost

SAR 15K

⁦4%⁩ of budget

Progress

⁦4%⁩Awaiting acceptance ⁦0%⁩

Estimate at completion

SAR 375K

SPI · CPI

1.00Schedule performance index · 1.001.00Cost performance index · 1.00

Forecast finish

⁦2027-12-31⁩

On baseline

PlanningStage ⁦3⁩ of ⁦5⁩

Next gate:Execution4 November 2026

  1. Pre-start · CompletePre-start · Complete
  2. Gate into «Initiation»DecisionConditional goDate17 June 2026Initiation · CompleteInitiation · Complete
  3. Gate into «Planning»DecisionGoDate16 August 2026Planning · Current stagePlanning · Current stage
  4. Gate into «Execution»DecisionNot held yetDate4 November 2026Execution · Not startedExecution · Not started
  5. Gate into «Closure»DecisionNot held yetClosure · Not startedClosure · Not started

Project status card

One page for the periodic update, to print or export and send to the committee and the sponsor.

Issue schedulePeriodic update cards

Shown by your permissionsProject Management Office: 1 project — everything in your scope

Riyadh ChamberMunjazStrategy & projectsMunjazPMO PLATFORM

Project status card

28 October 2026 · 17 Jumada I 1448 AH

Training Centre e-Learning Platform

PRJ-2026-029 · Training & Employment Centre · Strategic · WP-2026-029

Not startedOn track3PlanningProject manager: Ghada A. Al-Shahrani · Sponsor: Eng. Turki A. Al-Anazi
Progress
⁦4%⁩ / ⁦4%⁩
SPI · CPI
1.00 · 1.00
Spend
SAR 15K / SAR 375K
Estimate at completion
SAR 375K

Schedule

On plan⁦4%⁩

Planned to date ⁦4%⁩

Forecast finish: 2027-12-313 Shaʻban 1449 AH · On time

SPI1.00Schedule performance index · 1.00CPI1.00Cost performance index · 1.00

Health dimensions

On track

Last update: 2026-10-154 Jumada I 1448 AH · Up to date

Deliverables

⁦1⁩ of ⁦1⁩ due deliverables accepted on time (⁦100%⁩)

Next milestones

  • Project plan approved2027-01-0527 Rajab 1448 AH
  • Designs approved2027-04-0124 Shawwal 1448 AH
  • Build complete2027-08-086 Rabiʻ I 1449 AH
  • Testing & acceptance complete2027-11-023 Jumada II 1449 AH

Top risks

  • None

Open impediments

  • None

Decisions and changes waiting

  • None

Copilot summary

The scope holds 1 project with a budget of SAR 0.4M: 1 on track and 0 red or critical. Weighted progress is 4% against 4% planned, spend SAR 0M, and EAC SAR 0.4M (SAR 0M under).

No project is more than a month behind baseline.

Riyadh Chamber of Commerce & Industry · prepared by Ghada A. Al-Shahrani in MunjazInternal

Status: On track ·Project page

Esc

Quick actions

Go to

Projects

↑↓to move↵to openEscto close